SR 710
Updated Oct 15, 2026 · Sourced from FDOT Work Program & Active Construction data
12 active and programmed projects across 3 counties and 2 agencies.
3 counties2 agencies
Following keeps this corridor in your Following list. Updates about it are not sent yet.
Follow this corridor
Keep track of the projects and bids along this corridor.
- New projects on this corridor
- Project status changes
We'll email you when there's something worth knowing. No spam.
- Projects
- 12
- Counties
- 3
- Agencies
- 2
- Program Value
- $154M
- Firms
- 3
- Statewide Rank
- #36
4 in construction
Martin, Okeechobee
FDOT District Four
1 of 12 costed
On corridor projects
of 458 corridors
Counts and rank are derived from public project records — indicative, not audited figures. Program value covers the 1 project with a published cost.
Network & map
Explore the SR 710 network
Discover related bids, projects and partner organizations across Florida.
Recent project activity
SR 710 From SR 70 To N. Of Interceptor Creekbridge #910065
Okeechobee
PROGRAMMED · FY 2027
SR 710 From US 441 To L-63 Canal
Okeechobee
PROGRAMMED · FY 2031
SR-710 From Martin/Okeechobee Co Line To Fplpower Plant Access Road
Martin
PROGRAMMED · FY 2026
SR-710/BEELINE Hwy From W Of Park Commerce Blvd To E Of Aviation Blvd
Palm Beach
Construction · FY 2028
SR-710/SW Warfield Blvd Fr Fpl Access Rd To SW Allapattah Rd
Martin
PROGRAMMED · FY 2031
Who's building this corridor
- De Moya Asphalt Joint Venture1 project · $154.0M
Relationship Network
Connections to projects, agencies, and firms along this corridor.
SR 710 From SR 70 To N. Of Interceptor Creekbridge #910065
Okeechobee · PROGRAMMED · FY 2027
SR 710 From US 441 To L-63 Canal
Okeechobee · PROGRAMMED · FY 2031
SR-710 From Martin/Okeechobee Co Line To Fplpower Plant Access Road
Martin · PROGRAMMED · FY 2026
SR-710/BEELINE Hwy From W Of Park Commerce Blvd To E Of Aviation Blvd
Palm Beach · Construction · FY 2028
SR-710/SW Warfield Blvd Fr Fpl Access Rd To SW Allapattah Rd
Martin · PROGRAMMED · FY 2031
SR-710/SW Warfield Blvd Fr SW Allapattah Rd To SW Van Buren Ave
Martin · PROGRAMMED · FY 2030
SR-710/SW Warfield Blvd Fr W Of SE 126 Bl Tookeechobee/Martin Co Line
Okeechobee · PROGRAMMED · FY 2030
SR-710/SW Warfield Blvd W Of Four Winds Ranch E Of SW Springhaven Ave
Martin · Construction · FY 2027
SR-710/SW Warfield Boulevard At CR-714/SW Martin Highway
Martin · Construction · FY 2030
SR-710/WARFIELD Blvd Fr SW Fox Brown Road To SW Allapattah Road
Martin · PROGRAMMED · FY 2029
SR710/SW Warfield Blvd Fr E Lettuce Creek Tookeechobee/Martin Co Line
Okeechobee · PROGRAMMED · FY 2030
State Road (S.R.) 710/Beeline Highway Reconstruction Project
Palm Beach · Construction · FY 2024 · Palm Beach
SR 710 carries projects in 3 counties.
- Martin6 projects
- Okeechobee4 projects
- Palm Beach2 projects
SR 710 is delivered by 2 agencies — no single agency site shows all of it.
Relationship Network
Connections to projects, agencies, and firms along this corridor. Click a name to recenter the graph; click an avatar to open its page.