SR-713/KINGS Hwy Fr500' S Of SR-70 To North Of Picos Road
Project summary
Capacity / Add Lanes on SR 713 in St. Lucie County.
FDOT District Four lists it as Programmed.
Scope of Work
- Capacity / Add Lanes
- Reconstruction
Categories derived from the FDOT Work Program work-mix code for this project.
Project Network Preview
Organizations
Key Contacts
Related Projects
Recent Activity
- Status changed · Complete → ProgrammedAug 20, 2026
Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.
Opportunity Signals
- 28
- contracts up for bid
- $125.7M
- value at stake
- 2027-08
- next expiry
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$125.7M of work bids here by 2029 — be first to know the moment each RFQ drops.
- Email notifications
- Activity dashboard
- Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2023), managed by FDOT District Four. Detailed fact sheets and outreach materials are published once construction approaches.
Project Timeline
- PlanningComplete
- DesignComplete
- ProcurementIn Progress
- ConstructionUpcoming
- CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Brief
SR-713/KINGS Hwy Fr500' S Of SR-70 To North Of Picos Road
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Contract
FDOT record- Contract
- T4477
- Prime contractor
- Halley Engineering Contractors, Inc.
- FDOT project manager
- Saira Rothschild
- Contract status
- Active
- Contract time (bid)
- 1,355 days
- Time added by adjustments
- 465 days
- Federal project number
- 7079006U
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
- Data sync: FDOT Work Program re-readSep 16, 2026Scheduled data sync — no project fact necessarily changed
- Detected change: Status changedAug 20, 2026Complete → Programmed
- Data sync: FDOT Construction Contracts re-readAug 18, 2026Scheduled data sync — no project fact necessarily changed
- Project milestone: Paid offAug 13, 2024FDOT Construction Contracts
- Project milestone: Estimated completionSep 10, 2023FDOT Construction Contracts
- Project milestone: Final acceptanceSep 8, 2023FDOT Construction Contracts
- Project milestone: Work beganSep 17, 2018FDOT Construction Contracts
- Project milestone: Notice to proceedJul 24, 2018FDOT Construction Contracts
- Project milestone: ExecutedJun 25, 2018FDOT Construction Contracts
- Project milestone: LetMay 23, 2018FDOT Construction Contracts
- Project milestone: Projected lettingMay 23, 2018FDOT Construction Contracts
What Changed
- Aug 20, 2026Status changedComplete → Programmed
Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.
Dates & milestones
- Program year
- FY 2023
Identifiers
- FPID
- 230256-6-52-01
- Work Program item
- 230256
- District
- FDOT D4
- County
- St. Lucie
- Road
- SR 713
- Work mix (FDOT)
- Add Lanes & Reconstr
- FDOT status name
- LINE ITEM REOPENED
Sources & Data Confidence
View source details (13 facts)Hide source details
Not available for this project: FDOT Active Construction, district project page, cost, schedule, prime contractor, route geometry, federal funding.
| Fact | Value | Source | As of |
|---|---|---|---|
| Project name | SR-713/KINGS Hwy Fr500' S Of SR-70 To North Of Picos Road | FDOT Work Program | Sep 16, 2026 |
| Status | Programmed | Derived from FDOT Work Program status (LINE ITEM REOPENED) | Sep 16, 2026 |
| FDOT status | LINE ITEM REOPENED | FDOT Work Program | Sep 16, 2026 |
| FPID | 230256-6-52-01 | FDOT Work Program | Sep 16, 2026 |
| Work Program item | 230256 | FDOT Work Program | Sep 16, 2026 |
| County | St. Lucie | FDOT Work Program | Sep 16, 2026 |
| Road | SR 713 | FDOT Work Program | Sep 16, 2026 |
| Limits | SR-713/KINGS Hwy Fr500' S Of SR-70 To North Of Picos Road | FDOT Work Program | Sep 16, 2026 |
| Scope of work | Capacity / Add Lanes · Reconstruction | Derived from FDOT Work Program work mix (Add Lanes & Reconstr) | Sep 16, 2026 |
| Program year | FY 2023 | FDOT Work Program | Sep 16, 2026 |
| Contract number | T4477 | FDOT Construction Contracts | Aug 18, 2026 |
| Contract let | 2018-05-23 | FDOT Construction Contracts | Aug 18, 2026 |
| Notice to proceed | 2018-07-24 | FDOT Construction Contracts | Aug 18, 2026 |
Every fact in this record links to its published source. Where two sources disagree, both are shown rather than averaged or picked.
Lane closures & detours
Loading closure information…
Source: FDOT Work Zone Data Exchange. Publication is voluntary and may be incomplete.
Project Network
The agency, firms, people and corridors on this project. Hover a row to highlight it, click to recenter, or filter by type in the legend.
28
+1 in last 90 days
Upcoming Bids
Confirmed · nearing bid
26
+1 in last 90 days
Upcoming Opportunities
CAP-backed · in FDOT D4
$125.7M
Total Opportunity Value
Potential by 2029
Aug 2027
Next Bid
Soonest incumbent expiry
2029
Forecast Horizon
Through 2029
Opportunity Signals
- Upcoming BidsConfirmed · incumbent contracts nearing bid28
- Upcoming OpportunitiesCAP-backed · within FDOT D426
Bid counts are sourced. Upcoming Opportunities are CAP-backed and district-level.
Never miss what happens next.
Monitor this project and we’ll alert you the moment there’s movement—opportunities, awards, funding changes, team updates, and key milestones.
28
Future opportunities
identified
$125.7M
Potential value
by 2029
Planning
In ProgressAward
UpcomingConstruction
UpcomingOperations
FutureOpportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Monitor This Project
Your intelligence team, on call.
On your dashboard
The project in your watch list, with its latest dated signal
Change alerts
Status, letting and contractor changes in your alerts inbox
Weekly email
A summary in the weeks the project changes