Projects
501 projects managed by FDOT District Four
Updated Jul 27, 2026 · Sourced from FDOT Work Program & Active Construction data
501
Total Projects
$1.8B
Total Value
463
Active Projects
38
Completed
Try:SR 5SR 9Browardor a project name / FPID
State Road (S.R.) 9/I-95 at S.R. 606/Oslo Road New Interchange and S.R. 606/Oslo Road Widening Project
S.R. 9/I-95 at S.R. 606/Oslo Road, S.R. 606/Oslo Road from west of S.R. 9/I-95 to SW 58th Avenue, and SW 82nd Avenue from S.R. 606/Oslo Road to 1 mile north of S.R. 606/Oslo Road
Prime
Halley Engineering Contractors, Inc.
Start
Aug 2023
Est. Completion
Oct 2027
Oslo Road From SW 82Nd Ave To 58Th Avenue
Prime
Halley Engineering Contractors, Inc.
Start
Aug 2023
Est. Completion
Oct 2027
State Road (S.R.) 510/85th Street Widening Project
S.R. 510/85th Street from S.R. 512/Sebastian Boulevard to west of 87th Street.
Prime
Timothy Rose Contracting, Inc.
Start
Oct 2025
Est. Completion
May 2028
State Road (S.R.) 656/17th Street East End of Bridge Rehabilitation and Improvements Project
From the west side to the east side of the S.R. 656/17th Street bridge
Prime
Vecellio & Grogan, Inc.
Start
Sep 2023
Est. Completion
May 2028
State Road (S.R.) 5/U.S. 1 Sidewalk Improvement Project
State Road (S.R.) 5/U.S. 1 from County Road (C.R.) 611/45th Street to south of 53rd Street in the City of Vero Beach.
Prime
Alexander Design + Build, LLC
Start
May 2025
Est. Completion
Jan 2026