State Road (S.R.) 9/I-95 at S.R. 606/Oslo Road New Interchange and S.R. 606/Oslo Road Widening Project
Under Construction FDOT D4 Indian River County, FL I-95Interchange
Last updated Oct 15, 2026
Project summary
Interchange on I-95 in Indian River County (S.R. 9/I-95: .5 mile north and south of S.R. 606/Oslo Road; S.R. 606/Oslo Road: From .5 mile west of S.R. 9/I-95 to 58th Avenue; and SW 82nd Avenue: From S.R. 606/Oslo Road to 1 mile north of S.R. 606/Oslo Road).
S.R. 9/I-95 at S.R. 606/Oslo Road, S.R. 606/Oslo Road from west of S.R. 9/I-95 to SW 58th Avenue, and SW 82nd Avenue from S.R. 606/Oslo Road to 1 mile north of S.R. 606/Oslo Road
Halley Engineering Contractors, Inc. has been building it for FDOT District Four since Aug 14, 2023. FDOT estimates the contract finishes on Oct 21, 2027.
Project cost
$95.8M
District project site
Contract T4639
$102M
Covers 4 projects
Prime contractor
Halley Engineering Contractors, Inc.
FDOT record
Aug 14, 202378% of contract time elapsed · 332 days from todayOct 21, 2027
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$125.7M of work bids here by 2029 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressAug 14, 2023 – Oct 21, 2027
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 1.0 miN0.25 mi
RoadwayI-95
CountyIndian River County
LengthS.R. 9/I-95: .5 mile north and south of S.R. 606/Oslo Road; S.R. 606/Oslo Road: From .5 mile west of S.R. 9/I-95 to 58th Avenue; and SW 82nd Avenue: From S.R. 606/Oslo Road to 1 mile north of S.R. 606/Oslo Road
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
S.R. 9/I-95 at S.R. 606/Oslo Road, S.R. 606/Oslo Road from west of S.R. 9/I-95 to SW 58th Avenue, and SW 82nd Avenue from S.R. 606/Oslo Road to 1 mile north of S.R. 606/Oslo Road
S.R. 9/I-95: .5 mile north and south of S.R. 606/Oslo Road; S.R. 606/Oslo Road: From .5 mile west of S.R. 9/I-95 to 58th Avenue; and SW 82nd Avenue: From S.R. 606/Oslo Road to 1 mile north of S.R. 606/Oslo Road
Project length
Interchange
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed78%
Of the 50 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion332 days
Remaining against FDOT's estimated contract completion date.
Cost sourcesDiffer by 45%
The district’s published project cost and the FDOT feed figure disagree beyond the threshold used to flag a conflict. Both are shown under Cost & funding and in Sources; neither is averaged or dropped.
Data freshness39 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 4 projects)Σ FDOT Active Construction lines · contract T4639
$102M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$52.4M
Project costFDOT district project site
$95.8M
Phase line item (41304825201)FDOT Active Construction
$48.6M
Contract line items
413048-2-52-01This phase$48.6M
413048-2-52-02$3.7M
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
S.R. 9/I-95 at S.R. 606/Oslo Road, S.R. 606/Oslo Road from west of S.R. 9/I-95 to SW 58th Avenue, and SW 82nd Avenue from S.R. 606/Oslo Road to 1 mile north of S.R. 606/Oslo Road
S.R. 9/I-95: .5 mile north and south of S.R. 606/Oslo Road; S.R. 606/Oslo Road: From .5 mile west of S.R. 9/I-95 to 58th Avenue; and SW 82nd Avenue: From S.R. 606/Oslo Road to 1 mile north of S.R. 606/Oslo Road