Project Summary
I-95 Interchange Atpioneer Trail
Scope of Work
- Interchange
I-95 INTERCHANGE AT PIONEER TRAIL - INTERCHANGE (NEW)
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
- Prime contractor
- P & S Paving, Inc.FDOT
- Contract
- T5793FDOT
- Construction cost (this project)
- $58.6MDerived
- FDOT project manager
- Frederick CoeFDOT
CEI, subconsultants, project team contacts and award history are part of Pro.
Project Location
Approximate route from FDOT construction data · I-95.
Project Network Preview
Organizations
Key Contacts
Related Projects
Related Projects
Nearby
- SR 600 At The Intersection Of Lockhart StVolusia County · 202611.3 mi away$1.1M
- SR A1A From SR 5 / S Ridgewood Ave To Davis StVolusia County · 20269.1 mi away$5.2M
- SR A1A From SR 5 / S Ridgewood Ave To Davis StVolusia County · 20269.1 mi away$1.4M
- SR-430 From Clyde Morris Blvd To E Of Beach StreetVolusia County · 2025 – 202612.5 mi away$12M
Opportunity Signals
- 27
- contracts up for bid
- $125.7M
- value at stake
- 2028-09
- next expiry
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$125.7M of work bids here by 2029 — be first to know the moment each RFQ drops.
Email notifications Activity dashboard Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Programmed in the FDOT Five-Year Work Program (FY 2025), managed by FDOT District Five. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete DesignComplete ProcurementComplete- ConstructionIn ProgressAug 8, 2025 – Feb 11, 2028
- CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
- RoadwayI-95
- CountyVolusia County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
I-95 Interchange Atpioneer Trail
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Aug 25, 2026- Contract time elapsed44%
Of the 30 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
- Estimated completion518 days
Remaining against FDOT's estimated contract completion date.
- Data freshness17 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
- Contract total (covers 2 projects)Σ FDOT Active Construction lines · contract T5793
- $60.4M
- Construction cost (this project)Σ FDOT Active Construction lines for this project
- $58.6M
- Phase line item (43629215201)FDOT Active Construction
- $58.6M
Contract
FDOT record- Contract
- T5793
- Prime contractor
- C.W. Roberts Contracting, Inc.
- FDOT project manager
- Frederick Coe
- Contract status
- Active
- Contract time (bid)
- 870 days
- Time added by adjustments
- 60 days
- Federal project number
- D523021B
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
- Project milestone: Estimated completionUpcomingFeb 23, 2028FDOT Construction Contracts
- Data sync: FDOT Active Construction re-readAug 25, 2026Scheduled data sync — no project fact necessarily changed
- Data sync: FDOT Work Program re-readAug 25, 2026Scheduled data sync — no project fact necessarily changed
- Data sync: FDOT Construction Contracts re-readAug 18, 2026Scheduled data sync — no project fact necessarily changed
- Project milestone: Work beganAug 8, 2025FDOT Construction Contracts
- Project milestone: Notice to proceedJul 1, 2025FDOT Construction Contracts
- Project milestone: ExecutedJun 3, 2025FDOT Construction Contracts
- Project milestone: LetApr 30, 2025FDOT Construction Contracts
- Project milestone: Projected lettingApr 30, 2025FDOT Construction Contracts
Related Projects
Nearby
- SR 600 At The Intersection Of Lockhart StVolusia County · 202611.3 mi away$1.1M
- SR A1A From SR 5 / S Ridgewood Ave To Davis StVolusia County · 20269.1 mi away$5.2M
- SR A1A From SR 5 / S Ridgewood Ave To Davis StVolusia County · 20269.1 mi away$1.4M
- SR-430 From Clyde Morris Blvd To E Of Beach StreetVolusia County · 2025 – 202612.5 mi away$12M
Dates & milestones
- Construction start
- Aug 8, 2025
- Contract completion (estimated)
- Feb 11, 2028
- Program year
- FY 2025
Identifiers
- FPID
- 436292-1-52-01
- Contract number
- T5793
- Work Program item
- 436292
- District
- FDOT D5
- County
- Volusia
- Road
- I-95
- Work mix (FDOT)
- Interchange (New)
- FDOT status name
- UNDER CONSTRUCTION
Sources & Data Confidence
View source details (21 facts)Hide source details
Not available for this project: district project page, federal funding.
| Fact | Value | Source | As of |
|---|---|---|---|
| Project name | I-95 Interchange Atpioneer Trail | FDOT Work Program | Aug 25, 2026 |
| Status | Under Construction | Derived from FDOT Work Program status (UNDER CONSTRUCTION) | Aug 25, 2026 |
| FDOT status | UNDER CONSTRUCTION | FDOT Work Program | Aug 25, 2026 |
| FPID | 436292-1-52-01 | FDOT Work Program | Aug 25, 2026 |
| Work Program item | 436292 | FDOT Work Program | Aug 25, 2026 |
| County | Volusia | FDOT Work Program | Aug 25, 2026 |
| Road | I-95 | FDOT Work Program | Aug 25, 2026 |
| Limits | I-95 Interchange Atpioneer Trail | FDOT Work Program | Aug 25, 2026 |
| Scope of work | Interchange | Derived from FDOT Work Program work mix (Interchange (New)) | Aug 25, 2026 |
| Program year | FY 2025 | FDOT Work Program | Aug 25, 2026 |
| Contract total (covers 2 projects) | $60.4M | Σ FDOT Active Construction lines · contract T5793 | Aug 25, 2026 |
| Construction cost (this project) | $58.6M | Σ FDOT Active Construction lines for this project | Aug 25, 2026 |
| Phase line item (43629215201) | $58.6M | FDOT Active Construction | Aug 25, 2026 |
| Construction start | 2025-08-08 | FDOT Active Construction | Aug 25, 2026 |
| Contract completion (estimated) | 2028-02-11 | FDOT Active Construction | Aug 25, 2026 |
| Contract number | T5793 | FDOT Construction Contracts | Aug 18, 2026 |
| Contract let | 2025-04-30 | FDOT Construction Contracts | Aug 18, 2026 |
| Notice to proceed | 2025-07-01 | FDOT Construction Contracts | Aug 18, 2026 |
| Prime contractor | P & S Paving, Inc. | FDOT Active Construction | Aug 25, 2026 |
| FDOT project manager | Frederick Coe | FDOT Active Construction | Aug 25, 2026 |
| Route geometry | Mapped route | FDOT Active Construction | Aug 25, 2026 |
Every fact in this record links to its published source. Where two sources disagree, both are shown rather than averaged or picked.
Lane closures & detours
Loading closure information…
Source: FDOT Work Zone Data Exchange. Publication is voluntary and may be incomplete.
Project Network
The agency, firms, people and corridors on this project. Hover a row to highlight it, click to recenter, or filter by type in the legend.
27
Upcoming Bids
Confirmed · nearing bid
25
Upcoming Opportunities
CAP-backed · in FDOT D5
$125.7M
Total Opportunity Value
Potential by 2029
Sep 2028
Next Bid
Soonest incumbent expiry
2029
Forecast Horizon
Through 2029
Opportunity Signals
Upcoming BidsConfirmed · incumbent contracts nearing bid27 Upcoming OpportunitiesCAP-backed · within FDOT D525
Bid counts are sourced. Upcoming Opportunities are CAP-backed and district-level.
Never miss what happens next.
Monitor this project and we’ll alert you the moment there’s movement—opportunities, awards, funding changes, team updates, and key milestones.
27
Future opportunities
identified
$125.7M
Potential value
by 2029
Planning
CompleteAward
CompleteConstruction
In ProgressOperations
FutureOpportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Monitor This Project
Your intelligence team, on call.
Real-time alerts
Instant notifications when important updates happen
Activity dashboard
See all project activity in one central place
Weekly intelligence digest
Curated summary of what matters most
Unlimited project tracking
Follow all the projects you care about