I-95 Express Phase 3C, I-95 from south of Hollywood Boulevard to south of Broward Boulevard
Under Construction FDOT D4 Broward County, FL I-95Interchange
Last updated Aug 25, 2026
Project Summary
Widening I-95 from I-595 to Broward Blvd to add managed express lanes in each direction. The project includes roadway widening, bridge modifications, ITS, and operational improvements to increase capacity and enhance safety and mobility.
Add express lanes
2 in each direction
Improve bridges
Over I-595 & local roads
ITS upgrades
Signals, cameras, DMS
Operational improvements
Access, signing, and more
Scope of Work
Interchange
Capacity / Add Lanes
I-95/I-595 EXPRESS LANES DIRECT CONNECT,I-95 FR STIRLING TO BROWARD BL - INTERCHANGE - ADD LANES
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
Prime contractor
Archer Western-De Moya Joint VeFDOT
Contract
E4S44FDOT
Project cost
$457MDistrict
FDOT project manager
Mark MoshierFDOT
CEI, subconsultants, project team contacts and award history are part of Pro.
Project Location
Approximate route from FDOT construction data · I-95.
Adds a second 95 Express Lane in each direction through south Broward and rebuilds the I-95/I-595 interchange with new Direct Connectors — plus a replaced SR 84 bridge, new Turnpike ramps, and corridor-wide resurfacing across roughly 9 miles of I-95 and I-595.
I-95 Improvements7
Reconstruction, milling, resurfacing, overbuild, widening, and/or restriping of I-95 from south of Hollywood Boulevard to south of Broward Boulevard to accommodate the following:
One additional Express Lane in each direction (2 lanes total in each direction), between south of Stirling Road and Broward Boulevard.
A southbound Express Lanes entrance and a northbound Express Lanes exit location, serving Sheridan Street and interchanges to the north for traffic to and from the south.
A northbound Express Lanes entrance and a southbound Express Lanes exit location, serving Sheridan Street and interchanges to the south for traffic to and from the north.
Construction of dual exits for the northbound and southbound exit ramps to Sheridan Street.
Dual right turn lane improvements at the ramp terminal for the I-95 northbound exit ramp movement to eastbound Griffin Road.
I-95/I-595 Direct Connectors between northbound and southbound 95 Express Lanes and I-595, to and from the west.
I-95/S.R. 84 Interchange modifications, including replacement of the westbound SR 84 bridge over I-95, to accommodate one additional Express Lane in each direction along I-95 and Direct Connectors to and from I-595.
I-595 Improvements4
Reconstruction, milling, resurfacing, overbuild, widening, and/or restriping of I-595 from S.R. 7 to I-95, including the I-595 bridges of Pond Apple Slough, to accommodate the following:
Additional auxiliary lanes along I-595 and to/from the Direct Connectors.
A new westbound I-595 exit ramp to Turnpike.
A new eastbound I-595 entrance ramp from Turnpike.
A new eastbound I-595 exit ramp to eastbound S.R. 84.
Other Work1
Other work includes bridge widening, bridge painting, ITS, Tolling/gantry, signage, ramp signalization, lighting, drainage, shoulder mounted sound walls, and retaining walls.
Scope of work as published in the FDOT fact sheet.
Project Health
as of Aug 25, 2026
Contract time elapsed100%
Of the 75 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion248 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Cost sourcesDiffer by 2.9%
Measured between the district’s published project cost and the FDOT feed figure. Below the threshold used to flag a conflict — shown so the gap is visible rather than inferred from the absence of a warning.
Data freshness18 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 2 projects)Σ FDOT Active Construction lines · contract E4S44
$458.7M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$443.6M
Project costFDOT district project site
$457M
Phase line item (40935425201)FDOT Active Construction
$443.6M
$49.3M / mileConstruction cost (this project) ÷ 9 miles
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗