State Road (S.R.) 7/U.S. 441 & Interstate Ramps, and the North Fork New River (C-12) Canal Improvements Project
Under Construction FDOT D4 Broward County, FL SR 7Capacity / Add Lanes
Last updated Aug 25, 2026
Project Summary
With limits on U.S. 441/S.R. 7 from Orange Drive to Riverland Road, and limits on the south side of the North Fork New River (C-12) Canal from U.S. 441/S.R. 7 to NW 31st Avenue/M.L.K. Jr. Avenue
Scope of Work
Interchange
Capacity / Add Lanes
I-595 EASTBOUND TO NORTHBOUND RAMP AT SR-7/US-441 - INTERCHA NGE - ADD LANES
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
Prime contractor
General Asphalt Company, LLCFDOT
Contract
T4712FDOT
Project cost
$9.1MDistrict
FDOT project manager
Christopher ComproskyFDOT
CEI, subconsultants, project team contacts and award history are part of Pro.
Project Location
Approximate route from FDOT construction data · SR 7.
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressSep 2, 2025 – Dec 1, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 1.5 miN0.5 mi
RoadwaySR 7
CountyBroward County
Length3.5 miles
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
With limits on U.S. 441/S.R. 7 from Orange Drive to Riverland Road, and limits on the south side of the North Fork New River (C-12) Canal from U.S. 441/S.R. 7 to NW 31st Avenue/M.L.K. Jr. Avenue
3.5 miles
Project length
Interchange · Capacity / Add Lanes
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Aug 25, 2026
Contract time elapsed82%
Of the 15 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion81 days
Remaining against FDOT's estimated contract completion date.
Cost sourcesDiffer by 62%
The district’s published project cost and the FDOT feed figure disagree beyond the threshold used to flag a conflict. Both are shown under Cost & funding and in Sources; neither is averaged or dropped.
Data freshness17 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 2 projects)Σ FDOT Active Construction lines · contract T4712
$9.1M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$3.5M
Project costFDOT district project site
$9.1M
Phase line item (44567315201)FDOT Active Construction
$3.2M
$987.6K / mileConstruction cost (this project) ÷ 3.5 miles
Contract line items
445673-1-52-01This phase$3.2M
445673-1-52-02$282.3K
445673-1-52-03$4.3K
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
With limits on U.S. 441/S.R. 7 from Orange Drive to Riverland Road, and limits on the south side of the North Fork New River (C-12) Canal from U.S. 441/S.R. 7 to NW 31st Avenue/M.L.K. Jr. Avenue