State Road (S.R.) 7/U.S. 441 at Royal Palm Boulevard/West Copans Road Intersection Improvements Project
Under ConstructionConstruction complete FDOT D4 Broward County, FL SR 7Traffic Signals
Last updated Oct 15, 2026
Project summary
Traffic Signals on S.R. 7 in Broward County (0.349 miles).
S.R. 7/US 441 from NW 24th Street to Royal Palm Boulevard/West Copans Road and Royal Palm Boulevard/West Copans Road from NW 57th Terrace/East River Drive to SR 7/US 441
Weekley Asphalt Paving, Inc. has been building it for FDOT District Four since Apr 4, 2025. FDOT's estimated contract completion was Apr 20, 2026.
Construction contract value
$4.3M
Contract T4701, this project only
Prime contractor
Weekley Asphalt Paving, Inc.
FDOT record
Apr 4, 2025100% of contract time elapsed · 215 days past the estimateApr 20, 2026
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$125.7M of work bids here by 2029 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressApr 4, 2025 – Apr 20, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 0.2 miN0.1 mi
RoadwaySR 7
CountyBroward County
Length0.349 miles
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
S.R. 7/US 441 from NW 24th Street to Royal Palm Boulevard/West Copans Road and Royal Palm Boulevard/West Copans Road from NW 57th Terrace/East River Drive to SR 7/US 441
0.349 miles
Project length
Traffic Signals
Scope of work
Construction complete
FDOT status
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed100%
Of the 13 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion215 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Cost sourcesDiffer by 7.3%
Measured between the district’s published project cost and the FDOT feed figure. Below the threshold used to flag a conflict — shown so the gap is visible rather than inferred from the absence of a warning.
Data freshness37 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract T4701
$4.3M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$4.3M
Project costFDOT district project site
$4M
Phase line item (44928215201)FDOT Active Construction
$4M
$12.2M / mileConstruction contract value ÷ 0.349 miles
Contract line items
449282-1-52-01This phase$4M
449282-1-52-02$20.7K
449282-1-52-25$290.9K
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
Data sync: FDOT Active Construction re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Work Program re-readSep 16, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Construction Contracts re-readAug 18, 2026
Scheduled data sync — no project fact necessarily changed
S.R. 7/US 441 from NW 24th Street to Royal Palm Boulevard/West Copans Road and Royal Palm Boulevard/West Copans Road from NW 57th Terrace/East River Drive to SR 7/US 441