Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 0.6 miN0.1 mi
RoadwaySR 804
CountyPalm Beach County
Length0.595 miles
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
From east of Orchid Grove Trail to Palm Isles Drive
0.595 miles
Project length
Resurfacing
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Aug 25, 2026
Contract time elapsed100%
Of the 6 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion58 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Cost sourcesDiffer by 0.5%
Measured between the district’s published project cost and the FDOT feed figure. Below the threshold used to flag a conflict — shown so the gap is visible rather than inferred from the absence of a warning.
Data freshness17 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract E4X90
$2.7M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$2.7M
Project costFDOT district project site
$2.7M
Phase line item (44843715201)FDOT Active Construction
$2.7M
$4.5M / mileConstruction contract value ÷ 0.595 miles
Contract line items
448437-1-52-01This phase$2.7M
448437-1-52-02$6.2K
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
Data sync: FDOT Active Construction re-readAug 25, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Work Program re-readAug 25, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Construction Contracts re-readAug 18, 2026
Scheduled data sync — no project fact necessarily changed