Traffic Operations Improvement Project State Road (S.R.) 842/Broward Boulevard at NW 33rd Avenue and S.R. 842/Broward Boulevard at SW 29th Avenue
Project summary
Traffic Operations on S.R. 842 in Broward County (1.262 miles).
S.R. 842/Broward Boulevard at NW 33rd Avenue and S.R. 842/Broward Boulevard at SW 29th Avenue
Arc Electric, Inc. is building it for FDOT District Four.
- Project cost
- $1.3M
- District project site
- Prime contractor
- Arc Electric, Inc.
- District record
Scope of Work
- Traffic Operations
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
- Prime contractor
- Arc Electric, Inc.District
- Contract
- E4Y25FDOT
- Project cost
- $1.3MDistrict
CEI, subconsultants, project team contacts and award history are part of Pro.
Project Network Preview
Organizations
Key Contacts
Related Projects
Recent Activity
- Status changed · Programmed → Open for PursuitAug 20, 2026
Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.
Opportunity Signals
- 28
- contracts up for bid
- $125.7M
- value at stake
- 2027-08
- next expiry
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$125.7M of work bids here by 2029 — be first to know the moment each RFQ drops.
- Email notifications
- Activity dashboard
- Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
- PlanningComplete
- DesignComplete
- ProcurementComplete
- ConstructionIn ProgressAugust 16, 2026 – Spring 2027
- CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Brief
S.R. 842/Broward Boulevard at NW 33rd Avenue and S.R. 842/Broward Boulevard at SW 29th Avenue
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Cost & funding
- Project costFDOT district project site
- $1.3M
Contract
FDOT record- Contract
- E4Y25
- Prime contractor
- Arc Electric Inc
- FDOT project manager
- Carolina Sanchez
- Contract status
- Active
- Contract time (bid)
- 136 days
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
- Project milestone: Estimated completionUpcomingDec 25, 2026FDOT Construction Contracts
- Data sync: FDOT Work Program re-readSep 16, 2026Scheduled data sync — no project fact necessarily changed
- Detected change: Status changedAug 20, 2026Programmed → Open for Pursuit
- Data sync: FDOT Construction Contracts re-readAug 18, 2026Scheduled data sync — no project fact necessarily changed
- Project milestone: Notice to proceedMay 14, 2026FDOT Construction Contracts
- Project milestone: ExecutedApr 16, 2026FDOT Construction Contracts
- Project milestone: LetMar 6, 2026FDOT Construction Contracts
- Project milestone: Projected lettingMar 6, 2026FDOT Construction Contracts
What Changed
- Aug 20, 2026Status changedProgrammed → Open for Pursuit
Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.
Dates & milestones
- Start (district)
- August 16, 2026
- Project completion (district schedule)
- Spring 2027Approx.
- Program year
- FY 2026
Identifiers
- FPID
- 451493-1-52-01
- District
- FDOT D4
- County
- Broward
- Road
- S.R. 842
- Work mix (FDOT)
- Traffic Ops Improvem
- FDOT status name
- UNDER CONSTRUCTION
Sources & Data Confidence
View source details (17 facts)Hide source details
Not available for this project: FDOT Active Construction, route geometry, federal funding.
| Fact | Value | Source | As of |
|---|---|---|---|
| Project name | Traffic Operations Improvement Project State Road (S.R.) 842/Broward Boulevard at NW 33rd Avenue and S.R. 842/Broward Boulevard at SW 29th Avenue | FDOT district project site | — |
| Status | Under Construction | Derived from FDOT Work Program status (UNDER CONSTRUCTION) | Sep 16, 2026 |
| FDOT status | UNDER CONSTRUCTION | FDOT Work Program | Sep 16, 2026 |
| FPID | 451493-1-52-01 | FDOT district project site | — |
| County | Broward | FDOT district project site | — |
| Road | S.R. 842 | FDOT district project site | — |
| Limits | S.R. 842/Broward Boulevard at NW 33rd Avenue and S.R. 842/Broward Boulevard at SW 29th Avenue | FDOT district project site | — |
| Project length | 1.262 miles | FDOT district project site | — |
| Scope of work | Traffic Operations | Derived from FDOT Work Program work mix (Traffic Ops Improvem) | Sep 16, 2026 |
| Program year | FY 2026 | FDOT Work Program | Sep 16, 2026 |
| Project cost | $1.3M | FDOT district project site | — |
| Construction start | August 16, 2026 | FDOT district project site | — |
| Project completion (district schedule) | Spring 2027 | FDOT district project site | — |
| Contract number | E4Y25 | FDOT Construction Contracts | Aug 18, 2026 |
| Contract let | 2026-03-06 | FDOT Construction Contracts | Aug 18, 2026 |
| Notice to proceed | 2026-05-14 | FDOT Construction Contracts | Aug 18, 2026 |
| Prime contractor | Arc Electric, Inc. | FDOT district project site | — |
Every fact in this record links to its published source. Where two sources disagree, both are shown rather than averaged or picked.
Lane closures & detours
Loading closure information…
Source: FDOT Work Zone Data Exchange. Publication is voluntary and may be incomplete.
Project Network
The agency, firms, people and corridors on this project. Hover a row to highlight it, click to recenter, or filter by type in the legend.
28
+1 in last 90 days
Upcoming Bids
Confirmed · nearing bid
26
+1 in last 90 days
Upcoming Opportunities
CAP-backed · in FDOT D4
$125.7M
Total Opportunity Value
Potential by 2029
Aug 2027
Next Bid
Soonest incumbent expiry
2029
Forecast Horizon
Through 2029
Opportunity Signals
- Upcoming BidsConfirmed · incumbent contracts nearing bid28
- Upcoming OpportunitiesCAP-backed · within FDOT D426
Bid counts are sourced. Upcoming Opportunities are CAP-backed and district-level.
Never miss what happens next.
Monitor this project and we’ll alert you the moment there’s movement—opportunities, awards, funding changes, team updates, and key milestones.
28
Future opportunities
identified
$125.7M
Potential value
by 2029
Planning
CompleteAward
CompleteConstruction
In ProgressOperations
FutureOpportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Monitor This Project
Your intelligence team, on call.
On your dashboard
The project in your watch list, with its latest dated signal
Change alerts
Status, letting and contractor changes in your alerts inbox
Weekly email
A summary in the weeks the project changes