Project summary
Traffic Signals on S.R. 806 and S.R. 704 in Palm Beach County (0.4 miles).
S.R. 806/Atlantic Avenue and Homewood Boulevard Intersection and S.R. 704/Okeechobee Boulevard and Haverhill Road Intersection
Weekley Asphalt Paving, Inc. has been building it for FDOT District Four since Oct 21, 2025. FDOT's estimated contract completion was Aug 8, 2026.
Construction contract value
$3.2M
Contract T4707, this project only
Prime contractor
Weekley Asphalt Paving, Inc.
FDOT record
Oct 21, 2025100% of contract time elapsed · 106 days past the estimateAug 8, 2026
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$125.7M of work bids here by 2029 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressOct 21, 2025 – Aug 8, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 0.2 miN5 mi
RoadwaySR 806
CountyPalm Beach County
Length0.4 miles
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
S.R. 806/Atlantic Avenue and Homewood Boulevard Intersection and S.R. 704/Okeechobee Boulevard and Haverhill Road Intersection
0.4 miles
Project length
Traffic Signals
Scope of work
Construction complete
FDOT status
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed100%
Of the 10 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion106 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Cost sourcesDiffer by 1.5%
Measured between the district’s published project cost and the FDOT feed figure. Below the threshold used to flag a conflict — shown so the gap is visible rather than inferred from the absence of a warning.
Data freshness37 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract T4707
$3.2M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$3.2M
Project costFDOT district project site
$3.2M
Phase line item (44928315201)FDOT Active Construction
$3.2M
$7.9M / mileConstruction contract value ÷ 0.4 miles
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
Data sync: FDOT Active Construction re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Work Program re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed
Detected change: Status changedAug 20, 2026
Under Construction → Complete
Data sync: FDOT Construction Contracts re-readAug 18, 2026
Scheduled data sync — no project fact necessarily changed
State Road (S.R.) 806/Atlantic Avenue and Homewood Boulevard Intersection and S.R. 704/Okeechobee Boulevard and Haverhill Road Intersection Improvements Project