Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressJan 26, 2026 – Jun 7, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
N
RoadwaySR A1A
CountyPalm Beach County
Length0.025 miles
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
State Road (S.R.) A1A at Boynton Inlet Bridge
0.025 miles
Project length
Bridge & Structures
Scope of work
Construction complete
FDOT status
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Aug 25, 2026
Contract time elapsed100%
Of the 4 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion96 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Cost sourcesIdentical
Measured between the district’s published project cost and the FDOT feed figure. Below the threshold used to flag a conflict — shown so the gap is visible rather than inferred from the absence of a warning.
Data freshness17 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract E4X82
$579.1K
Construction cost (this project)Σ FDOT Active Construction lines for this project
$579.1K
Project costFDOT district project site
$579K
Phase line item (44925615201)FDOT Active Construction
$579.1K
$23.2M / mileConstruction contract value ÷ 0.025 miles
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
Data sync: FDOT Active Construction re-readAug 25, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Work Program re-readAug 25, 2026
Scheduled data sync — no project fact necessarily changed
Detected change: Status changedAug 20, 2026
Under Construction → Complete
Data sync: FDOT Construction Contracts re-readAug 18, 2026
Scheduled data sync — no project fact necessarily changed