State Road (S.R.) 714/SW Martin Highway from east of SW Stuart W Boulevard to west of Citrus Boulevard
Project Summary
From east of SW Stuart West Boulevard to west of Citrus Boulevard
Scope of Work
- Resurfacing
SR-714/SW MARTIN HWY FROM E OF SW STUART W BLVD TO W OF CITR US BLVD - RESURFACING
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
- Prime contractor
- Halley Engineering Contractors, Inc.FDOT
- Contract
- E4X83FDOT
- Construction contract value
- $3.5MDerived
- FDOT project manager
- Sara StoreyFDOT
CEI, subconsultants, project team contacts and award history are part of Pro.
Project Location
Approximate route from FDOT construction data · SR 714.
Project Network Preview
Organizations
Key Contacts
Related Projects
Recent Activity
- Status changed · Open for Pursuit → Under ConstructionAug 20, 2026
Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.
Related Projects
Nearby
- Southwest Port St. Lucie Boulevard Widening Project1.076 miles · St. Lucie County · 2025 – 20285.0 mi away$22.2M
- SR-5/US-1 Fr S Of Martin/St Lucie County Line To SE Port St Lucie BlvdSt. Lucie County · 2025 – 20268.2 mi away$3.1M
- State Road (S.R.) 5/U.S. 1 Resurfacing, Restoration, and Rehabilitation Project1.724 miles · Martin County · 2025 – 20267.2 mi away$7.5M
- State Road (S.R.) 716/Southeast Port St. Lucie Boulevard and S.R. 5/US 1 Resurfacing, Restoration, and Rehabilitation (RRR) Project0.669 miles · St. Lucie County · 2025 – 20268.1 mi away$3.7M
Opportunity Signals
- 31
- contracts up for bid
- $136.7M
- value at stake
- 2027-08
- next expiry
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$136.7M of work bids here by 2029 — be first to know the moment each RFQ drops.
Email notifications Activity dashboard Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
PlanningComplete DesignComplete ProcurementComplete- ConstructionIn ProgressOct 13, 2026
- CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
- RoadwaySR 714
- CountyMartin County
- Length3.314
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
From east of SW Stuart West Boulevard to west of Citrus Boulevard
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Aug 25, 2026- Estimated completion31 days
Remaining against FDOT's estimated contract completion date.
- Cost sourcesIdentical
Measured between the district’s published project cost and the FDOT feed figure. Below the threshold used to flag a conflict — shown so the gap is visible rather than inferred from the absence of a warning.
- Data freshness17 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
- Construction contract valueΣ FDOT Active Construction lines · contract E4X83
- $3.5M
- Construction cost (this project)Σ FDOT Active Construction lines for this project
- $3.5M
- Project costFDOT district project site
- $3.5M
- Phase line item (44844615201)FDOT Active Construction
- $3.5M
Contract
FDOT record- Contract
- E4X83
- Prime contractor
- Halley Engineering Contractors, Inc.
- FDOT project manager
- Sara Storey
- Contract status
- Active
- Contract time (bid)
- 212 days
- Time added by adjustments
- 3 days
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
- Project milestone: Estimated completionUpcomingNov 13, 2026FDOT Construction Contracts
- Data sync: FDOT Active Construction re-readAug 25, 2026Scheduled data sync — no project fact necessarily changed
- Data sync: FDOT Work Program re-readAug 25, 2026Scheduled data sync — no project fact necessarily changed
- Detected change: Status changedAug 20, 2026Open for Pursuit → Under Construction
- Data sync: FDOT Construction Contracts re-readAug 18, 2026Scheduled data sync — no project fact necessarily changed
- Project milestone: Work beganApr 13, 2026FDOT Construction Contracts
- Project milestone: Notice to proceedOct 2, 2025FDOT Construction Contracts
- Project milestone: ExecutedSep 4, 2025FDOT Construction Contracts
- Project milestone: LetJul 11, 2025FDOT Construction Contracts
- Project milestone: Projected lettingJul 11, 2025FDOT Construction Contracts
What Changed
- Aug 20, 2026Status changedOpen for Pursuit → Under Construction
Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.
Related Projects
Nearby
- Southwest Port St. Lucie Boulevard Widening Project1.076 miles · St. Lucie County · 2025 – 20285.0 mi away$22.2M
- SR-5/US-1 Fr S Of Martin/St Lucie County Line To SE Port St Lucie BlvdSt. Lucie County · 2025 – 20268.2 mi away$3.1M
- State Road (S.R.) 5/U.S. 1 Resurfacing, Restoration, and Rehabilitation Project1.724 miles · Martin County · 2025 – 20267.2 mi away$7.5M
- State Road (S.R.) 716/Southeast Port St. Lucie Boulevard and S.R. 5/US 1 Resurfacing, Restoration, and Rehabilitation (RRR) Project0.669 miles · St. Lucie County · 2025 – 20268.1 mi away$3.7M
Dates & milestones
- Contract completion (estimated)
- Oct 13, 2026
- Project completion (district schedule)
- Fall 2026Approx.
- Program year
- FY 2026
Identifiers
- FPID
- 448446-1-52-01
- Contract number
- E4X83
- District
- FDOT D4
- County
- Martin
- Road
- S.R. 714
- Work mix (FDOT)
- Resurfacing
- FDOT status name
- UNDER CONSTRUCTION
Sources & Data Confidence
View source details (22 facts)Hide source details
Not available for this project: federal funding.
| Fact | Value | Source | As of |
|---|---|---|---|
| Project name | State Road (S.R.) 714/SW Martin Highway from east of SW Stuart W Boulevard to west of Citrus Boulevard | FDOT district project site | — |
| Status | Under Construction | Derived from FDOT Work Program status (UNDER CONSTRUCTION) | Aug 25, 2026 |
| FDOT status | UNDER CONSTRUCTION | FDOT Work Program | Aug 25, 2026 |
| FPID | 448446-1-52-01 | FDOT district project site | — |
| County | Martin | FDOT district project site | — |
| Road | S.R. 714 | FDOT district project site | — |
| Limits | From east of SW Stuart West Boulevard to west of Citrus Boulevard | FDOT district project site | — |
| Project length | 3.314 | FDOT district project site | — |
| Scope of work | Resurfacing | Derived from FDOT Work Program work mix (Resurfacing) | Aug 25, 2026 |
| Program year | FY 2026 | FDOT Work Program | Aug 25, 2026 |
| Construction contract value | $3.5M | Σ FDOT Active Construction lines · contract E4X83 | Aug 25, 2026 |
| Construction cost (this project) | $3.5M | Σ FDOT Active Construction lines for this project | Aug 25, 2026 |
| Project cost | $3.5M | FDOT district project site | — |
| Phase line item (44844615201) | $3.5M | FDOT Active Construction | Aug 25, 2026 |
| Contract completion (estimated) | 2026-10-13 | FDOT Active Construction | Aug 25, 2026 |
| Project completion (district schedule) | Fall 2026 | FDOT district project site | — |
| Contract number | E4X83 | FDOT Construction Contracts | Aug 18, 2026 |
| Contract let | 2025-07-11 | FDOT Construction Contracts | Aug 18, 2026 |
| Notice to proceed | 2025-10-02 | FDOT Construction Contracts | Aug 18, 2026 |
| Prime contractor | Halley Engineering Contractors, Inc. | FDOT Active Construction | Aug 25, 2026 |
| FDOT project manager | Sara Storey | FDOT Active Construction | Aug 25, 2026 |
| Route geometry | Mapped route | FDOT Active Construction | Aug 25, 2026 |
Every fact in this record links to its published source. Where two sources disagree, both are shown rather than averaged or picked.
Lane closures & detours
Loading closure information…
Source: FDOT Work Zone Data Exchange. Publication is voluntary and may be incomplete.
Project Network
The agency, firms, people and corridors on this project. Hover a row to highlight it, click to recenter, or filter by type in the legend.
31
Upcoming Bids
Confirmed · nearing bid
29
Upcoming Opportunities
CAP-backed · in FDOT D4
$136.7M
Total Opportunity Value
Potential by 2029
Aug 2027
Next Bid
Soonest incumbent expiry
2029
Forecast Horizon
Through 2029
Opportunity Signals
Upcoming BidsConfirmed · incumbent contracts nearing bid31 Upcoming OpportunitiesCAP-backed · within FDOT D429
Bid counts are sourced. Upcoming Opportunities are CAP-backed and district-level.
Never miss what happens next.
Monitor this project and we’ll alert you the moment there’s movement—opportunities, awards, funding changes, team updates, and key milestones.
31
Future opportunities
identified
$136.7M
Potential value
by 2029
Planning
CompleteAward
CompleteConstruction
In ProgressOperations
FutureOpportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Monitor This Project
Your intelligence team, on call.
Real-time alerts
Instant notifications when important updates happen
Activity dashboard
See all project activity in one central place
Weekly intelligence digest
Curated summary of what matters most
Unlimited project tracking
Follow all the projects you care about