Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressJan 5, 2026 – Aug 16, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 1.0 miN0.25 mi
RoadwaySR A1A
CountyBroward County
Length1.015 miles
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
Flamingo Avenue to South of Pine Ave
1.015 miles
Project length
Resurfacing
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Aug 25, 2026
Contract time elapsed100%
Of the 7 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion27 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Cost sourcesIdentical
Measured between the district’s published project cost and the FDOT feed figure. Below the threshold used to flag a conflict — shown so the gap is visible rather than inferred from the absence of a warning.
Data freshness18 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract E4Y06
$2.6M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$2.6M
Project costFDOT district project site
$2.6M
Phase line item (44840515201)FDOT Active Construction
$2.4M
$2.6M / mileConstruction contract value ÷ 1.015 miles
Contract line items
448405-1-52-01This phase$2.4M
448405-1-52-02$213K
448405-1-52-03$51.5K
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗