State Road (S.R.) 870/Commercial Boulevard Resurfacing, Restoration, and Rehabilitation (RRR) and Intelligent Transportation System (ITS) Improvements Project
Under Construction FDOT D4 Broward County, FL SR 870Roadway Improvements
Last updated Aug 25, 2026
Project Summary
S.R. 870/Commercial Boulevard from S.R. 817/University Drive to SR A1A/North Ocean Drive.
Scope of Work
Resurfacing
SR-870/COMMERCIAL BLVD FR SR-845/POWERLINE RD TO E OF A1A/N OCEAN DR - RESURFACING
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
Prime contractor
Sice IncFDOT
Contract
T4692FDOT
Project cost
$25.7MDistrict
FDOT project manager
Christopher ComproskyFDOT
CEI, subconsultants, project team contacts and award history are part of Pro.
Project Location
Approximate route from FDOT construction data · SR 870.
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressJan 6, 2025 – Oct 8, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 3.7 miN1 mi
RoadwaySR 870
CountyBroward County
Length9.89 miles
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
S.R. 870/Commercial Boulevard from S.R. 817/University Drive to SR A1A/North Ocean Drive.
9.89 miles
Project length
Resurfacing
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Aug 25, 2026
Contract time elapsed96%
Of the 21 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion26 days
Remaining against FDOT's estimated contract completion date.
Cost sourcesDiffer by 39%
The district’s published project cost and the FDOT feed figure disagree beyond the threshold used to flag a conflict. Both are shown under Cost & funding and in Sources; neither is averaged or dropped.
Data freshness17 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 3 projects)Σ FDOT Active Construction lines · contract T4692
$25.7M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$15.7M
Project costFDOT district project site
$25.7M
Phase line item (44618215201)FDOT Active Construction
$15.5M
$1.6M / mileConstruction cost (this project) ÷ 9.89 miles
Contract line items
446182-1-52-01This phase$15.5M
446182-1-52-02$37.6K
446182-1-52-03$188.6K
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
State Road (S.R.) 870/Commercial Boulevard Resurfacing, Restoration, and Rehabilitation (RRR) and Intelligent Transportation System (ITS) Improvements Project