Traffic Signal Mast Arm Replacement Project
Project Summary
Various locations in Palm Beach County along S.R. 5, S.R. 805, S.R. 9, S.R. A1A, and S.R. 786 in the Cities of Boca Raton, Lake Worth Beach, Palm Beach Gardens, Riviera Beach, and West Palm Beach
Scope of Work
- Traffic Signals
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
- Prime contractor
- SICE Inc.District
- Contract
- T4735FDOT
- Project cost
- $3.4MDistrict
CEI, subconsultants, project team contacts and award history are part of Pro.
Project Network Preview
Organizations
Key Contacts
Related Projects
Opportunity Signals
- 35
- contracts up for bid
- $153.5M
- value at stake
- 2027-08
- next expiry
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$153.5M of work bids here by 2029 — be first to know the moment each RFQ drops.
- Email notifications
- Activity dashboard
- Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
- PlanningComplete
- DesignComplete
- ProcurementComplete
- ConstructionIn ProgressSeptember 2026 – Summer 2027
- CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Brief
Various locations in Palm Beach County along S.R. 5, S.R. 805, S.R. 9, S.R. A1A, and S.R. 786 in the Cities of Boca Raton, Lake Worth Beach, Palm Beach Gardens, Riviera Beach, and West Palm Beach
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Cost & funding
- Project costFDOT district project site
- $3.4M
Contract
FDOT record- Contract
- T4735
- Prime contractor
- Sice Inc
- FDOT project manager
- Woodler Blaise
- Contract status
- Active
- Contract time (bid)
- 224 days
- Federal project number
- D425076B
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
- Project milestone: Estimated completionUpcomingApr 14, 2027FDOT Construction Contracts
- Data sync: FDOT Work Program re-readAug 30, 2026Scheduled data sync — no project fact necessarily changed
- Data sync: FDOT Construction Contracts re-readAug 18, 2026Scheduled data sync — no project fact necessarily changed
- Project milestone: Notice to proceedJun 5, 2026FDOT Construction Contracts
- Project milestone: ExecutedMay 7, 2026FDOT Construction Contracts
- Project milestone: LetMar 25, 2026FDOT Construction Contracts
- Project milestone: Projected lettingMar 25, 2026FDOT Construction Contracts
Dates & milestones
- Start (district)
- September 2026
- Project completion (district schedule)
- Summer 2027Approx.
- Program year
- FY 2026
Identifiers
- FPID
- 451579-2-52-01
- Member FPIDs (2)
- 451579-2-52-01451579-2-52-02
- District
- FDOT D4
- County
- Palm Beach
- Road
- State Road (S.R.) 5, S.R. 805, S.R. 9, S.R. A1A, and S.R. 786
- Work mix (FDOT)
- Traffic Signals
- FDOT status name
- CONTRACT EXECUTED
Sources & Data Confidence
View source details (17 facts)Hide source details
Not available for this project: FDOT Active Construction, route geometry, federal funding.
| Fact | Value | Source | As of |
|---|---|---|---|
| Project name | Traffic Signal Mast Arm Replacement Project | FDOT district project site | — |
| Status | Under Construction | Derived from FDOT Work Program status (CONTRACT EXECUTED) | Aug 30, 2026 |
| FDOT status | CONTRACT EXECUTED | FDOT Work Program | Aug 30, 2026 |
| FPID | 451579-2-52-01 | FDOT district project site | — |
| County | Palm Beach | FDOT district project site | — |
| Road | State Road (S.R.) 5, S.R. 805, S.R. 9, S.R. A1A, and S.R. 786 | FDOT district project site | — |
| Limits | Various locations in Palm Beach County along S.R. 5, S.R. 805, S.R. 9, S.R. A1A, and S.R. 786 in the Cities of Boca Raton, Lake Worth Beach, Palm Beach Gardens, Riviera Beach, and West Palm Beach | FDOT district project site | — |
| Project length | 1.292 miles | FDOT district project site | — |
| Scope of work | Traffic Signals | Derived from FDOT Work Program work mix (Traffic Signals) | Aug 30, 2026 |
| Program year | FY 2026 | FDOT Work Program | Aug 30, 2026 |
| Project cost | $3.4M | FDOT district project site | — |
| Construction start | September 2026 | FDOT district project site | — |
| Project completion (district schedule) | Summer 2027 | FDOT district project site | — |
| Contract number | T4735 | FDOT Construction Contracts | Aug 18, 2026 |
| Contract let | 2026-03-25 | FDOT Construction Contracts | Aug 18, 2026 |
| Notice to proceed | 2026-06-05 | FDOT Construction Contracts | Aug 18, 2026 |
| Prime contractor | SICE Inc. | FDOT district project site | — |
Every fact in this record links to its published source. Where two sources disagree, both are shown rather than averaged or picked.
Lane closures & detours
Loading closure information…
Source: FDOT Work Zone Data Exchange. Publication is voluntary and may be incomplete.
Related Open Positions
No open posting names this project. These are open roles at FDOT D4 in Palm Beach County — not confirmed as this project's roles.
Project Network
The agency, firms, people and corridors on this project. Hover a row to highlight it, click to recenter, or filter by type in the legend.
35
Upcoming Bids
Confirmed · nearing bid
33
Upcoming Opportunities
CAP-backed · in FDOT D4
$153.5M
Total Opportunity Value
Potential by 2029
Aug 2027
Next Bid
Soonest incumbent expiry
2029
Forecast Horizon
Through 2029
Opportunity Signals
- Upcoming BidsConfirmed · incumbent contracts nearing bid35
- Upcoming OpportunitiesCAP-backed · within FDOT D433
Bid counts are sourced. Upcoming Opportunities are CAP-backed and district-level.
Never miss what happens next.
Monitor this project and we’ll alert you the moment there’s movement—opportunities, awards, funding changes, team updates, and key milestones.
35
Future opportunities
identified
$153.5M
Potential value
by 2029
Planning
CompleteAward
CompleteConstruction
In ProgressOperations
FutureOpportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Monitor This Project
Your intelligence team, on call.
Real-time alerts
Instant notifications when important updates happen
Activity dashboard
See all project activity in one central place
Weekly intelligence digest
Curated summary of what matters most
Unlimited project tracking
Follow all the projects you care about