State Road (S.R.) 93/I-75 Alligator Alley Resurfacing, Restoration, and Rehabilitation (RRR) Project – Section 2

Under ConstructionConstruction complete FDOT D4 Broward County, FL I-75Roadway Improvements
Last updated Aug 25, 2026

Project Summary

Mile Post (MP) 31.261 to the Everglades Toll Plaza (MP 18.873)

Scope of Work

  • Resurfacing

SR-93/I-75/ALLIGATOR ALLEY FR TOLL PLAZA TO MP 31.261 - RESU RFACING

Categories derived from the FDOT Work Program work-mix code for this project.

Contracts & Awards

Prime contractor
Ranger Construction Industries, Inc.FDOT
Contract
E4X54FDOT
Construction contract value
$25.3MDerived
FDOT project manager
Matthew MayFDOT

CEI, subconsultants, project team contacts and award history are part of Pro.

Project Location

≈ 12 miN2 mi

Approximate route from FDOT construction data · I-75.

Project Network Preview

3

Organizations

4

Key Contacts

24

Related Projects

Recent Activity

  1. Status changed · Under Construction → CompleteAug 20, 2026

Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.

Opportunity Signals

32
contracts up for bid
$136.7M
value at stake
2027-08
next expiry

Counts and totals only. Incumbents, contract rows and bid timing are Pro.

Don’t get scooped on this work.

$136.7M of work bids here by 2029 — be first to know the moment each RFQ drops.

Follow Project
  • Email notifications
  • Activity dashboard
  • Cancel anytime

Opportunity announcements

New RFQs, RFPs, Solicitations

Contract awards

Winners, Award values, Award dates

Team & consultant changes

New firms, Teaming updates, Incumbent changes

Milestone & funding updates

Funding changes, Key milestones

Related corridor activity

New corridor projects

Unlock with TransitAtlas Pro to get full project intelligence and alerts.

Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site