State Road (S.R.) 70/Okeechobee Road Resurfacing Project
Under ConstructionConstruction complete FDOT D4 St. Lucie County, FL SR 70Roadway Improvements
Last updated Oct 15, 2026
Project summary
Resurfacing on S.R. 70 in St. Lucie County (7.9 miles).
S.R. 70/Okeechobee Road from Ideal Holding Road to west of S.R. 713/Kings Highway
Halley Engineering Contractors, Inc. has been building it for FDOT District Four since Mar 20, 2025. FDOT estimates the contract finishes on Dec 24, 2026.
Construction contract value
$18.2M
Contract T4700, this project only
Prime contractor
Halley Engineering Contractors, Inc.
FDOT record
Mar 20, 202595% of contract time elapsed · 30 days from todayDec 24, 2026
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$125.7M of work bids here by 2029 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressMar 20, 2025 – Dec 24, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 8.0 miN1 mi
RoadwaySR 70
CountySt. Lucie County
Length7.9 miles
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
S.R. 70/Okeechobee Road from Ideal Holding Road to west of S.R. 713/Kings Highway
7.9 miles
Project length
Resurfacing
Scope of work
Construction complete
FDOT status
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed95%
Of the 21 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion30 days
Remaining against FDOT's estimated contract completion date.
Cost sourcesDiffer by 7.4%
Measured between the district’s published project cost and the FDOT feed figure. Below the threshold used to flag a conflict — shown so the gap is visible rather than inferred from the absence of a warning.
Data freshness39 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract T4700
$18.2M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$18.2M
Project costFDOT district project site
$16.9M
Phase line item (44765315201)FDOT Active Construction
$17M
$2.3M / mileConstruction contract value ÷ 7.9 miles
Contract line items
447653-1-52-01This phase$17M
447653-1-52-25$1.2M
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗