TransitAtlas
All FDOT District Four projects

East Las Olas Boulevard Bridge Rehabilitation Project

Under Construction FDOT D4 Broward County, FL SR 842Bridge
Last updated Oct 15, 2026

Project summary

Bridge & Structures on S.R. 842 in Broward County (0.207 miles).

Seacoast Incorporated is building it for FDOT District Four. FDOT estimates the contract finishes on Apr 23, 2027.

Construction contract value
$14.1M
Contract E4X35, this project only
Prime contractor
Seacoast Incorporated
FDOT record
View on the source site

The route, raised from the 2D map

≈ 0.2 miN0.1 mi
Approximate route from FDOT construction data · SR 842.

Scope of Work

  • Bridge & Structures

SR-842/LAS OLAS BLVD OVER ICWW - BROWARD COUNTY - BRIDGE-REP AIR/REHABILITATION

Categories derived from the FDOT Work Program work-mix code for this project.

Contracts & Awards

Prime contractor
Seacoast IncorporatedFDOT
Contract
E4X35FDOT
Construction contract value
$14.1MDerived
FDOT project manager
Jesus SarmientoFDOT

CEI, subconsultants, project team contacts and award history are part of Pro.

Project Network Preview

3

Organizations

4

Key Contacts

11

Related Projects

Recent Activity

  1. Status changed · Open for Pursuit → Under ConstructionAug 20, 2026

Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.

Opportunity Signals

28
contracts up for bid
$125.7M
value at stake
2027-08
next expiry

Counts and totals only. Incumbents, contract rows and bid timing are Pro.

Don’t get scooped on this work.

$125.7M of work bids here by 2029 — be first to know the moment each RFQ drops.

  • Email notifications
  • Activity dashboard
  • Cancel anytime

Opportunity announcements

New RFQs, RFPs, Solicitations

Contract awards

Winners, Award values, Award dates

Team & consultant changes

New firms, Teaming updates, Incumbent changes

Milestone & funding updates

Funding changes, Key milestones

Related corridor activity

New corridor projects

Unlock with TransitAtlas Pro to get full project intelligence and alerts.

Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site