State Road (S.R.) 806/Atlantic Avenue Reconstruction Project
Under Construction FDOT D4 Palm Beach County, FL SR 806Capacity / Add Lanes
Last updated Aug 25, 2026
Project Summary
S.R. 806/Atlantic Avenue, from west of S.R. 7/US 441 to just east of S.R. 91/Florida’s Turnpike, and on S.R. 7/US 441, from just south of Rio Grande Avenue to just south of Tivoli Island Boulevard
Scope of Work
Capacity / Add Lanes
Reconstruction
SR-806/ATLANTIC AVE FROM WEST OF SR-7/US-441 TO EAST OF LYON S ROAD - ADD LANES & RECONSTRUCT
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
Prime contractor
Ohla USA IncFDOT
Contract
T4655FDOT
Project cost
$26MDistrict
FDOT project manager
Ricky EstipeautFDOT
CEI, subconsultants, project team contacts and award history are part of Pro.
Project Location
Approximate route from FDOT construction data · SR 806.
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressJan 21, 2025 – Feb 21, 2028
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 1.3 miN0.25 mi
RoadwaySR 806
CountyPalm Beach County
Length2.760 miles
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
S.R. 806/Atlantic Avenue, from west of S.R. 7/US 441 to just east of S.R. 91/Florida’s Turnpike, and on S.R. 7/US 441, from just south of Rio Grande Avenue to just south of Tivoli Island Boulevard
2.760 miles
Project length
Capacity / Add Lanes · Reconstruction
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Aug 25, 2026
Contract time elapsed53%
Of the 37 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion527 days
Remaining against FDOT's estimated contract completion date.
Cost sourcesDiffer by 20%
The district’s published project cost and the FDOT feed figure disagree beyond the threshold used to flag a conflict. Both are shown under Cost & funding and in Sources; neither is averaged or dropped.
Data freshness18 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 3 projects)Σ FDOT Active Construction lines · contract T4655
$28M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$20.9M
Project costFDOT district project site
$26M
Phase line item (22965845201)FDOT Active Construction
$18.5M
$7.6M / mileConstruction cost (this project) ÷ 2.760 miles
Contract line items
229658-4-52-01This phase$18.5M
229658-4-52-02$389.9K
229658-4-52-25$2M
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
S.R. 806/Atlantic Avenue, from west of S.R. 7/US 441 to just east of S.R. 91/Florida’s Turnpike, and on S.R. 7/US 441, from just south of Rio Grande Avenue to just south of Tivoli Island Boulevard