S.R. 9/I-95 northbound exit ramp to eastbound S.R. 862/I-595 ramp
Florida Engineering & Development Corp has been building it for FDOT District Four since Jan 5, 2026. FDOT's estimated contract completion was Sep 16, 2026.
Construction contract value
$5.3M
Contract T4724, this project only
Prime contractor
Florida Engineering & Development Corp
FDOT record
Jan 5, 2026100% of contract time elapsed · 69 days past the estimateSep 16, 2026
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$125.7M of work bids here by 2029 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressJan 5, 2026 – Sep 16, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 0.4 miN0.1 mi
RoadwayI-95
Length0.4 miles
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
S.R. 9/I-95 northbound exit ramp to eastbound S.R. 862/I-595 ramp
0.4 miles
Project length
Capacity / Add Lanes
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed100%
Of the 8 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion69 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Cost sourcesIdentical
Measured between the district’s published project cost and the FDOT feed figure. Below the threshold used to flag a conflict — shown so the gap is visible rather than inferred from the absence of a warning.
Data freshness39 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract T4724
$5.3M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$5.3M
Project costFDOT district project site
$5.3M
Phase line item (44172315201)FDOT Active Construction
$5.3M
$13.2M / mileConstruction contract value ÷ 0.4 miles
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗