TransitAtlas
All FDOT District One projects

SR 25 (US 27) From Shoreline Dr To Davis & Gaines Rd

Under Construction FDOT D1 Highlands County, FL SR 25Roadway Improvements
Last updated Oct 15, 2026

Project summary

Resurfacing on SR 25 in Highlands County.

C.W. Roberts Contracting, Inc. has been building it for FDOT District One since Nov 20, 2024. FDOT's estimated contract completion was Aug 2, 2026.

Construction cost (this project)
$23.1M
Sum of 2 FDOT line items
Contract T1894
$27.9M
Covers 2 projects
Prime contractor
C.W. Roberts Contracting, Inc.
FDOT record
Federal funding traced
$14.3M
FHWA award, matched by title
Nov 20, 2024100% of contract time elapsed · 113 days past the estimateAug 2, 2026
View in the FDOT Work Program

The route, raised from the 2D map

≈ 6.4 miN2 mi
Approximate route from FDOT construction data · SR 25.

Scope of Work

  • Resurfacing

SR 25 (US 27) FROM SHORELINE DR TO DAVIS & GAINES RD - RESUR FACING

Categories derived from the FDOT Work Program work-mix code for this project.

Contracts & Awards

Prime contractor
C.W. Roberts Contracting, Inc.FDOT
Contract
T1894FDOT
Construction cost (this project)
$23.1MDerived
FDOT project manager
Stacy HillFDOT

CEI, subconsultants, project team contacts and award history are part of Pro.

Funding & origin

Federal
$14.3MMatched by title
federal funding traced across 1 award
Federal Highway AdministrationFDOT D1This project

Source: USASpending.gov, fetched 2026-06-20. Matched by FHWA project title near-exact match — "SR 25 (US 27) FROM SHORELINE DR TO DAVIS & GAINES RD".

Project Network Preview

2

Organizations

1

Key Contacts

24

Related Projects

Opportunity Signals

11
contracts up for bid
$32.7M
value at stake

Counts and totals only. Incumbents, contract rows and bid timing are Pro.

Don’t get scooped on this work.

$32.7M of work bids here — be first to know the moment each RFQ drops.

  • Email notifications
  • Activity dashboard
  • Cancel anytime

Opportunity announcements

New RFQs, RFPs, Solicitations

Contract awards

Winners, Award values, Award dates

Team & consultant changes

New firms, Teaming updates, Incumbent changes

Milestone & funding updates

Funding changes, Key milestones

Related corridor activity

New corridor projects

Unlock with TransitAtlas Pro to get full project intelligence and alerts.

Programmed in the FDOT Five-Year Work Program (FY 2024), managed by FDOT District One. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program