Projects
622 projects managed by FDOT District One
Updated Sep 6, 2026 · Sourced from FDOT Work Program & Active Construction data
622
Total Projects
$1.2B
Total Value
596
Active Projects
26
Completed
34 of 622
Filters
Try:I-75SR 45Polkor a project name / FPID
Phase
Corridor
County
Contractors
Work Type
Fiscal Year
Project Value
Status
Sort
1 active· 34 of 622CorridorI-75
Clear allSarasota10 projects · $189.4M
I-75I-75 (SR 93) At Fruitville Road/Cr 780
Prince Contracting, LLC.Oct 2024–Mar 20295 nearby
$177.0MActive
I-75I-75 At Toledo Blade Interchange Improvements
Ajax Paving Industries Of Florida LLCApr 2025–Mar 20271 nearby
$6.9MActive
I-75I-75 At Sumter Blvdinterchange Improvements
Ajax Paving Industries Of Florida LLCApr 2025–Mar 20272 nearby
$5.5MActive
Lee9 projects · $42.5M
I-75I-75 (SR 93) At CR 876 / Daniels Parkway
Watson Civil Construction, Inc.Jan 2026–Mar 20284 nearby
$42.5MActive
Collier7 projects · $151.3M
I-75I-75 (SR 93) At SR 951
The De Moya Group Inc.Sep 2022–Sep 20263 nearby
$97.9MCompleted
I-75I-75 (SR 93) From Mile Point 33.989 To Mile Point 46.000
Ohla USA IncDec 2024–Apr 20261 nearby
$28.5MCompleted
I-75I-75 At Pine Ridge Road
Sacyr Construccion SaMar 2025–Jan 20272 nearby
$25.0MActive
Manatee5 projects · $3.1M
I-75I-75 (SR 93) Adms From Sarasota County Line To I-275
Transcore ITS, LLC.May 2025–Nov 20267 nearby
$3.1MActive