US92/SR600/GANDY Bridge EB #100300 Over Tampa Bay

Under Construction FDOT D7 Hillsborough County, FL US 92Bridge
Last updated Oct 15, 2026

Project summary

Bridge & Structures on US 92 in Hillsborough County.

Structural Technologies, LLC has been building it for FDOT District Seven since Nov 3, 2025. FDOT estimates the contract finishes on Dec 24, 2026.

Construction contract value
$2.9M
Contract E7Q97, this project only
Prime contractor
Structural Technologies, LLC
FDOT record
Nov 3, 202593% of contract time elapsed · 30 days from todayDec 24, 2026

The route, raised from the 2D map

≈ 2.8 miN0.5 mi
Approximate route from FDOT construction data · US 92.

Scope of Work

  • Bridge & Structures

US92/SR600/GANDY BRIDGE EB #100300 OVER TAMPA BAY - BRIDGE-R EPAIR/REHABILITATION

Categories derived from the FDOT Work Program work-mix code for this project.

Contracts & Awards

Prime contractor
Structural Technologies, LLCFDOT
Contract
E7Q97FDOT
Construction contract value
$2.9MDerived
FDOT project manager
Farhad ZafaranianFDOT

CEI, subconsultants, project team contacts and award history are part of Pro.

Project Network Preview

2

Organizations

1

Key Contacts

21

Related Projects

Opportunity Signals

9
contracts up for bid
$111.8M
value at stake
2026-05
next expiry

Counts and totals only. Incumbents, contract rows and bid timing are Pro.

Don’t get scooped on this work.

$111.8M of work bids here by 2026 — be first to know the moment each RFQ drops.

  • Email notifications
  • Activity dashboard
  • Cancel anytime

Opportunity announcements

New RFQs, RFPs, Solicitations

Contract awards

Winners, Award values, Award dates

Team & consultant changes

New firms, Teaming updates, Incumbent changes

Milestone & funding updates

Funding changes, Key milestones

Related corridor activity

New corridor projects

Unlock with TransitAtlas Pro to get full project intelligence and alerts.

Programmed in the FDOT Five-Year Work Program (FY 2025), managed by FDOT District Seven. Detailed fact sheets and outreach materials are published once construction approaches.