CR 30A Over Westernlake, Bridge

Under Construction FDOT D3 Walton County, FL CR 30Bridge
Last updated Oct 15, 2026

Project summary

Bridge & Structures on CR 30 in Walton County.

Rj Gorman Contracting LLC has been building it for FDOT District Three since Jan 3, 2024. FDOT's estimated contract completion was Feb 28, 2026.

Construction contract value
$12.5M
Contract T3788, this project only
Prime contractor
Rj Gorman Contracting LLC
FDOT record
Jan 3, 2024100% of contract time elapsed · 267 days past the estimateFeb 28, 2026
View in the FDOT Work Program

The route, raised from the 2D map

≈ 0.3 miN0.1 mi
Approximate route from FDOT construction data · CR 30.

Scope of Work

  • Bridge & Structures

CR 30A OVER WESTERN LAKE, BRIDGE 600089 - BRIDGE REPLACEMENT

Categories derived from the FDOT Work Program work-mix code for this project.

Contracts & Awards

Prime contractor
Rj Gorman Contracting LLCFDOT
Contract
T3788FDOT
Construction contract value
$12.5MDerived
FDOT project manager
Eric RosensteinFDOT

CEI, subconsultants, project team contacts and award history are part of Pro.

Project Network Preview

2

Organizations

1

Key Contacts

3

Related Projects

Opportunity Signals

37
contracts up for bid
$135.1M
value at stake
2030-09
next expiry

Counts and totals only. Incumbents, contract rows and bid timing are Pro.

Don’t get scooped on this work.

$135.1M of work bids here by 2030 — be first to know the moment each RFQ drops.

  • Email notifications
  • Activity dashboard
  • Cancel anytime

Opportunity announcements

New RFQs, RFPs, Solicitations

Contract awards

Winners, Award values, Award dates

Team & consultant changes

New firms, Teaming updates, Incumbent changes

Milestone & funding updates

Funding changes, Key milestones

Related corridor activity

New corridor projects

Unlock with TransitAtlas Pro to get full project intelligence and alerts.

Programmed in the FDOT Five-Year Work Program (FY 2024), managed by FDOT District Three. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program