Under Construction FDOT D2 Duval County, FL I-295Roadway Improvements
Last updated Oct 15, 2026
Project summary
ITS / Technology on I-295 in Duval County.
The Guarantee Company Of North America USA has been building it for FDOT District Two since Jul 9, 2019. FDOT's estimated contract completion was Jan 22, 2024.
Construction cost (this project)
$3.9M
Sum of 1 FDOT line item
Contract T2692
$18.1M
Covers 2 projects
Prime contractor
The Guarantee Company Of North America USA
FDOT record
Jul 9, 2019100% of contract time elapsed · 1,036 days past the estimateJan 22, 2024
The route, raised from the 2D map
Arrow keys pan, plus and minus zoom, Q and E turn. On a touch screen, turn and pinch with two fingers.
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$57.5M of work bids here — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2023), managed by FDOT District Two. Detailed fact sheets and outreach materials are published once construction approaches.
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressJul 9, 2019 – Jan 22, 2024
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 1.4 miN0.5 mi
RoadwayI-295
CountyDuval County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
I-295 Signs Update For Express Lanes
ITS / Technology
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed100%
Of the 54 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion1,036 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Data freshness39 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 2 projects)Σ FDOT Active Construction lines · contract T2692
$18.1M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$3.9M
Phase line item (43817115201)FDOT Active Construction
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
Data sync: FDOT Active Construction re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Work Program re-readSep 16, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Construction Contracts re-readAug 18, 2026
Scheduled data sync — no project fact necessarily changed