SR26(NEWBERRY Rd) From West Of CR241 South To West Of I-75(SR93)

Under Construction FDOT D2 Alachua County, FL SR 26Roadway Improvements
Last updated Oct 15, 2026

Project summary

Resurfacing on SR 26 in Alachua County.

Preferred Materials Inc. has been building it for FDOT District Two since Jun 11, 2025. FDOT's estimated contract completion was Aug 20, 2026.

Construction contract value
$11.5M
Contract T2A07, this project only
Prime contractor
Preferred Materials Inc.
FDOT record
Jun 11, 2025100% of contract time elapsed · 94 days past the estimateAug 20, 2026
View in the FDOT Work Program

The route, raised from the 2D map

≈ 6.2 miN1 mi
Approximate route from FDOT construction data · SR 26.

Scope of Work

  • Resurfacing

SR26(NEWBERRY RD) FROM WEST OF CR241 SOUTH TO WEST OF I-75(S R93) - RESURFACING

Categories derived from the FDOT Work Program work-mix code for this project.

Contracts & Awards

Prime contractor
Preferred Materials Inc.FDOT
Contract
T2A07FDOT
Construction contract value
$11.5MDerived
FDOT project manager
William WimpyFDOT

CEI, subconsultants, project team contacts and award history are part of Pro.

Project Network Preview

2

Organizations

1

Key Contacts

24

Related Projects

Opportunity Signals

16
contracts up for bid
$57.5M
value at stake

Counts and totals only. Incumbents, contract rows and bid timing are Pro.

Don’t get scooped on this work.

$57.5M of work bids here — be first to know the moment each RFQ drops.

  • Email notifications
  • Activity dashboard
  • Cancel anytime

Opportunity announcements

New RFQs, RFPs, Solicitations

Contract awards

Winners, Award values, Award dates

Team & consultant changes

New firms, Teaming updates, Incumbent changes

Milestone & funding updates

Funding changes, Key milestones

Related corridor activity

New corridor projects

Unlock with TransitAtlas Pro to get full project intelligence and alerts.

Programmed in the FDOT Five-Year Work Program (FY 2025), managed by FDOT District Two. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program