Hps To Led Lightingconversion Tpkwide - Phase I Broward/Palm Beach
Under Construction Turnpike Turnpike County, FLLighting
Last updated Oct 15, 2026
Project summary
Lighting on Hps To Led Lightingconversion Tpkwide - Phase I Broward/Palm Beach in Turnpike County.
Horsepower Electric, Inc. has been building it for Florida's Turnpike Enterprise since Nov 3, 2025. FDOT estimates the contract finishes on Dec 28, 2026.
Construction contract value
$5.4M
Contract E8V61, this project only
Prime contractor
Horsepower Electric, Inc.
FDOT record
Nov 3, 202591% of contract time elapsed · 36 days from todayDec 28, 2026
The route, raised from the 2D map
Arrow keys pan, plus and minus zoom, Q and E turn. On a touch screen, turn and pinch with two fingers.
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$156.7M of work bids here by 2028 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2025), managed by Florida's Turnpike Enterprise. Detailed fact sheets and outreach materials are published once construction approaches.
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressNov 3, 2025 – Dec 28, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 3.8 miN10 mi
CountyTurnpike County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
Hps To Led Lightingconversion Tpkwide - Phase I Broward/Palm Beach
Lighting
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed91%
Of the 14 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion36 days
Remaining against FDOT's estimated contract completion date.
Data freshness38 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract E8V61
$5.4M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$5.4M
Phase line item (45222875201)FDOT Active Construction
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗