Under Construction Turnpike Seminole County, FLSafety
Last updated Oct 15, 2026
Project summary
Safety on Safety Improvementsseminole Xway (SR417) (MP49-56) Seminole Cnty in Seminole County.
Masci General Contractors, Inc has been building it for Florida's Turnpike Enterprise since Aug 14, 2025. FDOT's estimated contract completion was Jul 30, 2026.
Construction cost (this project)
$5.1M
Sum of 1 FDOT line item
Contract E8V62
$17.4M
Covers 2 projects
Prime contractor
Masci General Contractors, Inc
FDOT record
Aug 14, 2025100% of contract time elapsed · 114 days past the estimateJul 30, 2026
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$156.7M of work bids here by 2028 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2025), managed by Florida's Turnpike Enterprise. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed100%
Of the 11 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion114 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Data freshness37 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 2 projects)Σ FDOT Active Construction lines · contract E8V62
$17.4M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$5.1M
Phase line item (44968725201)FDOT Active Construction
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
Data sync: FDOT Active Construction re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Work Program re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed