Under Construction Turnpike Palm Beach County, FLCapacity / Add Lanes
Last updated Oct 15, 2026
Project summary
Capacity / Add Lanes on Widen Tpk(Sr91) Boynton Bch Blvd-Lake Worth Rd(4-8Lns) Mp87-94Mngd Ln in Palm Beach County.
Johnson Bros. Corporation, A Southland Company has been building it for Florida's Turnpike Enterprise since Sep 9, 2019. FDOT estimates the contract finishes on Dec 5, 2026.
Construction cost (this project)
$202.2M
Sum of 3 FDOT line items
Contract E8Q79
$202.3M
Covers 2 projects
Prime contractor
Johnson Bros. Corporation, A Southland Company
FDOT record
Sep 9, 2019100% of contract time elapsed · 12 days from todayDec 5, 2026
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$156.7M of work bids here by 2028 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2023), managed by Florida's Turnpike Enterprise. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressSep 9, 2019 – Dec 5, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 7.0 miN2 mi
CountyPalm Beach County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed100%
Of the 87 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion12 days
Remaining against FDOT's estimated contract completion date.
Data freshness39 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 2 projects)Σ FDOT Active Construction lines · contract E8Q79
$202.3M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$202.2M
Phase line item (40614415201)FDOT Active Construction
$199.5M
Contract line items
406144-1-52-01This phase$199.5M
406144-1-52-02$308.8K
406144-1-52-03$2.3M
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗