TransitAtlas
All FDOT District Five projects

SR A1A Sidewalk From SR 518 To Volunteer Way

Under Construction FDOT D5 Brevard County, FLBicycle & Pedestrian
Last updated Oct 15, 2026

Project summary

Bicycle & Pedestrian on SR A1A Sidewalk in Brevard County.

Alexander Design + Build, LLC has been building it for FDOT District Five since Mar 17, 2025. FDOT's estimated contract completion was Jan 20, 2026.

Construction contract value
$2.1M
Contract T5829, this project only
Prime contractor
Alexander Design + Build, LLC
FDOT record
Mar 17, 2025100% of contract time elapsed · 305 days past the estimateJan 20, 2026
View in the FDOT Work Program

The route, raised from the 2D map

≈ 1.1 miN0.25 mi
Approximate route from FDOT construction data.

Scope of Work

  • Bicycle & Pedestrian

SR A1A SIDEWALK FROM SR 518 TO VOLUNTEER WAY - SIDEWALK

Categories derived from the FDOT Work Program work-mix code for this project.

Contracts & Awards

Prime contractor
Alexander Design + Build, LLCFDOT
Contract
T5829FDOT
Construction contract value
$2.1MDerived
FDOT project manager
Robert MarcouxFDOT

CEI, subconsultants, project team contacts and award history are part of Pro.

Project Network Preview

2

Organizations

1

Key Contacts

2

Related Projects

Opportunity Signals

23
contracts up for bid
$88.1M
value at stake
2028-09
next expiry

Counts and totals only. Incumbents, contract rows and bid timing are Pro.

Don’t get scooped on this work.

$88.1M of work bids here by 2028 — be first to know the moment each RFQ drops.

  • Email notifications
  • Activity dashboard
  • Cancel anytime

Opportunity announcements

New RFQs, RFPs, Solicitations

Contract awards

Winners, Award values, Award dates

Team & consultant changes

New firms, Teaming updates, Incumbent changes

Milestone & funding updates

Funding changes, Key milestones

Related corridor activity

New corridor projects

Unlock with TransitAtlas Pro to get full project intelligence and alerts.

Programmed in the FDOT Five-Year Work Program (FY 2025), managed by FDOT District Five. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program