Projects
457 projects managed by FDOT District Five
Updated Jul 27, 2026 · Sourced from FDOT Work Program & Active Construction data
457
Total Projects
$1.3B
Total Value
401
Active Projects
56
Completed
Try:I-95SR 40Orangeor a project name / FPID
I-95 From SR514 (Malabar Rd) To Concrete Joint N Of SR519 (Fiske Blvd)
Prime
P & S Paving, Inc.
Start
Mar 2025
Est. Completion
Dec 2026
I-95 Southbound Rest Area
Prime
Southland Construction, Inc.
Start
Sep 2024
Est. Completion
Apr 2026
I-95/SR 9 From South Of SR 50 To SR 46
Prime
Masci General Contractors, Inc
Start
Jan 2026
Est. Completion
Mar 2027
SR 500 / US 192 From I-95 To SR 507 ( Babcock St )
Prime
Preferred Materials Inc.
Start
Oct 2024
Est. Completion
Feb 2026
SR-5 From Minnie Ln To The Volusia County Line
Prime
P & S Paving, Inc.
Start
Jan 2025
Est. Completion
Apr 2026
SR 3 Over Barge Canal Movable Bridge Rehab
Prime
Seacoast Incorporated
Est. Completion
Feb 2026
SR 404 From SR 5 Tosr A1A
Prime
Masci General Contractors, Inc
Start
Sep 2025
Est. Completion
May 2026
SR 513 From SR 518 To Patrick Space Force Base
Prime
Ohla USA Inc
Est. Completion
Mar 2026
US 1/SR 5 From Myers Dr To Crane Creek Bridge #700006
Prime
Timothy Rose Contracting, Inc.
Start
Sep 2025
Est. Completion
Jun 2026
SR 5 / US 1 From North Of Century Oaks Circle To North Of Myers Drive
Prime
V.A. Paving, Inc.
Start
Oct 2025
Est. Completion
May 2026
SR401 Resurfacing From SR528 To Canaveral Space Force Station
Prime
Masci General Contractors, Inc
Start
Jun 2025
Est. Completion
Jan 2026
SR 401 Over Canaveral Barge Canal
Prime
Drax, Inc.
Start
Apr 2025
Est. Completion
Jan 2026
SR 518 (Eau Gallie Blvd) From Sarno Rd To West Of Apollo Blvd
Prime
Preferred Materials Inc.
Start
Dec 2025
Est. Completion
Apr 2026
SR 519 (Fiske Blvd) From Barbara Jenkins To SR 520 (King St)
Prime
Carr Construction, LLC
Est. Completion
May 2026
SR A1A Sidewalk From SR 518 To Volunteer Way
Prime
Alexander Design + Build, LLC
Start
Mar 2025
Est. Completion
Jan 2026
SR 514 From West Ofi-95 To East Of SR 507 /Babcock St
Prime
Pigott Asphalt And Sitework LLC
Start
Feb 2026
Est. Completion
Jun 2026
SR 519/Fiske Blvd At Levitt Parkway/Lakemourblvd Signalization
Prime
Carr Construction, LLC
Est. Completion
May 2026
SR 5 (US 1) From South Of Fay Blvd To North Of Fay Blvd
Prime
Chinchor Electric Inc.
Est. Completion
May 2026