Project summary

Safety on SR 80 in Lee County.

Wright Construction Group, Inc. has been building it for FDOT District One since Oct 3, 2025. FDOT's estimated contract completion was Jun 2, 2026.

Construction cost (this project)
$5.2M
Sum of 1 FDOT line item
Contract T1898
$7.2M
Covers 2 projects
Prime contractor
Wright Construction Group, Inc.
FDOT record
Oct 3, 2025100% of contract time elapsed · 174 days past the estimateJun 2, 2026
View in the FDOT Work Program

The route, raised from the 2D map

≈ 2.3 miN0.5 mi
Approximate route from FDOT construction data · SR 80.

Scope of Work

  • Safety

SR 80 FROM VERONICA SHOEMAKER TO KINGSTON DR - SAFETY PROJEC T

Categories derived from the FDOT Work Program work-mix code for this project.

Contracts & Awards

Prime contractor
Wright Construction Group, Inc.FDOT
Contract
T1898FDOT
Construction cost (this project)
$5.2MDerived
FDOT project manager
Mollitor ChrisFDOT

CEI, subconsultants, project team contacts and award history are part of Pro.

Project Network Preview

2

Organizations

1

Key Contacts

10

Related Projects

Opportunity Signals

11
contracts up for bid
$32.7M
value at stake

Counts and totals only. Incumbents, contract rows and bid timing are Pro.

Don’t get scooped on this work.

$32.7M of work bids here — be first to know the moment each RFQ drops.

  • Email notifications
  • Activity dashboard
  • Cancel anytime

Opportunity announcements

New RFQs, RFPs, Solicitations

Contract awards

Winners, Award values, Award dates

Team & consultant changes

New firms, Teaming updates, Incumbent changes

Milestone & funding updates

Funding changes, Key milestones

Related corridor activity

New corridor projects

Unlock with TransitAtlas Pro to get full project intelligence and alerts.

Programmed in the FDOT Five-Year Work Program (FY 2025), managed by FDOT District One. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program