Under Construction FDOT D1 Hendry County, FL SR 82Bicycle & Pedestrian
Last updated Oct 15, 2026
Project summary
Bicycle & Pedestrian on SR 82 in Hendry County.
Ajax Paving Industries Of Florida LLC has been building it for FDOT District One since Sep 23, 2024. FDOT estimates the contract finishes on Oct 5, 2027.
Construction cost (this project)
$1.1M
Sum of 1 FDOT line item
Contract T1865
$57.1M
Covers 2 projects
Prime contractor
Ajax Paving Industries Of Florida LLC
FDOT record
Sep 23, 202471% of contract time elapsed · 316 days from todayOct 5, 2027
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$32.7M of work bids here — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2024), managed by FDOT District One. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressSep 23, 2024 – Oct 5, 2027
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 1.3 miN0.25 mi
RoadwaySR 82
CountyHendry County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
SR 82 From Lee County Line To Collier Countyline
Bicycle & Pedestrian
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed71%
Of the 36 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion316 days
Remaining against FDOT's estimated contract completion date.
Data freshness39 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 2 projects)Σ FDOT Active Construction lines · contract T1865
$57.1M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$1.1M
Phase line item (43084825201)FDOT Active Construction
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗