SR52 At SR589 (Suncoast Trail)

Under Construction FDOT D7 Pasco County, FL SR 52Bicycle & Pedestrian
Last updated Oct 15, 2026

Project summary

Bicycle & Pedestrian on SR 52 in Pasco County.

Cone & Graham, Inc. has been building it for FDOT District Seven since Jan 5, 2026. FDOT estimates the contract finishes on Jan 20, 2027.

Construction contract value
$9.9M
Contract E7Q51, this project only
Prime contractor
Cone & Graham, Inc.
FDOT record
Jan 5, 202685% of contract time elapsed · 57 days from todayJan 20, 2027
View in the FDOT Work Program

The route, raised from the 2D map

N
Approximate route from FDOT construction data · SR 52.

Scope of Work

  • Bicycle & Pedestrian

SR52 AT SR589 (SUNCOAST TRAIL) - PEDESTRIAN/WILDLIFE OVERPAS S

Categories derived from the FDOT Work Program work-mix code for this project.

Contracts & Awards

Prime contractor
Cone & Graham, Inc.FDOT
Contract
E7Q51FDOT
Construction contract value
$9.9MDerived
FDOT project manager
Kenneth WilsonFDOT

CEI, subconsultants, project team contacts and award history are part of Pro.

Project Network Preview

2

Organizations

1

Key Contacts

11

Related Projects

Opportunity Signals

9
contracts up for bid
$111.8M
value at stake
2026-05
next expiry

Counts and totals only. Incumbents, contract rows and bid timing are Pro.

Don’t get scooped on this work.

$111.8M of work bids here by 2026 — be first to know the moment each RFQ drops.

  • Email notifications
  • Activity dashboard
  • Cancel anytime

Opportunity announcements

New RFQs, RFPs, Solicitations

Contract awards

Winners, Award values, Award dates

Team & consultant changes

New firms, Teaming updates, Incumbent changes

Milestone & funding updates

Funding changes, Key milestones

Related corridor activity

New corridor projects

Unlock with TransitAtlas Pro to get full project intelligence and alerts.

Programmed in the FDOT Five-Year Work Program (FY 2025), managed by FDOT District Seven. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program