TransitAtlas
All FDOT District Seven projects

I75/SR93 Interchange Improvement At SR 52

Under Construction FDOT D7 Pasco County, FL I-75Interchange
Last updated Oct 15, 2026

Project summary

Interchange on I-75 in Pasco County.

C.W. Roberts Contracting, Inc. is building it for FDOT District Seven. FDOT's estimated contract completion was Apr 8, 2026.

Construction contract value
$2M
Contract E7U39, this project only
Prime contractor
C.W. Roberts Contracting, Inc.
FDOT record
View in the FDOT Work Program

The route, raised from the 2D map

≈ 0.5 miN0.1 mi
Approximate route from FDOT construction data · I-75.

Scope of Work

  • Interchange

I75/SR93 INTERCHANGE IMPROVEMENT AT SR 52 - INTERCHANGE IMPR OVEMENT

Categories derived from the FDOT Work Program work-mix code for this project.

Contracts & Awards

Prime contractor
C.W. Roberts Contracting, Inc.FDOT
Contract
E7U39FDOT
Construction contract value
$2MDerived
FDOT project manager
Alejandro PinaFDOT

CEI, subconsultants, project team contacts and award history are part of Pro.

Project Network Preview

2

Organizations

1

Key Contacts

24

Related Projects

Recent Activity

  1. Status changed · Open for Pursuit → Under ConstructionAug 20, 2026

Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.

Opportunity Signals

9
contracts up for bid
$111.8M
value at stake
2026-05
next expiry

Counts and totals only. Incumbents, contract rows and bid timing are Pro.

Don’t get scooped on this work.

$111.8M of work bids here by 2026 — be first to know the moment each RFQ drops.

  • Email notifications
  • Activity dashboard
  • Cancel anytime

Opportunity announcements

New RFQs, RFPs, Solicitations

Contract awards

Winners, Award values, Award dates

Team & consultant changes

New firms, Teaming updates, Incumbent changes

Milestone & funding updates

Funding changes, Key milestones

Related corridor activity

New corridor projects

Unlock with TransitAtlas Pro to get full project intelligence and alerts.

Programmed in the FDOT Five-Year Work Program (FY 2026), managed by FDOT District Seven. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program