SR 5/US 1 Long Key Bridge Over Long Key Channel (Bridge
Under Construction FDOT D6 Monroe County, FL SR 5Bridge
Last updated Oct 15, 2026
Project summary
Bridge & Structures on SR 5 in Monroe County.
M & J Construction Company Of Pinellas County, Inc. has been building it for FDOT District Six since Feb 13, 2023. FDOT's estimated contract completion was Aug 3, 2026.
Construction contract value
$4.7M
Contract E6O03, this project only
Prime contractor
M & J Construction Company Of Pinellas County, Inc.
FDOT record
Feb 13, 2023100% of contract time elapsed · 112 days past the estimateAug 3, 2026
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$74.3M of work bids here by 2030 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2023), managed by FDOT District Six. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressFeb 13, 2023 – Aug 3, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 2.3 miN0.5 mi
RoadwaySR 5
CountyMonroe County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
SR 5/US 1 Long Key Bridge Over Long Key Channel (Bridge 900094)
Bridge & Structures
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed100%
Of the 42 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion112 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Data freshness38 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract E6O03
$4.7M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$4.7M
Phase line item (44196415201)FDOT Active Construction
M & J Construction Company Of Pinellas County, Inc.
FDOT project manager
Tony Sabbag
Contract status
Active
Contract time (bid)
500 days
Time added by adjustments
791 days
Cross-check · contracts feed$4.7M
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
Data sync: FDOT Active Construction re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Work Program re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed