SR5/US1 Overseas Hwy Seven Mile Bridge Over Moser Channel- Br#

Under Construction FDOT D6 Monroe County, FL SR 5Bridge
Last updated Oct 15, 2026

Project summary

Bridge & Structures on SR 5 in Monroe County.

Freyssinet, Inc. is building it for FDOT District Six. FDOT estimates the contract finishes on Mar 8, 2029.

Construction contract value
$17.7M
Contract E6P31, this project only
Prime contractor
Freyssinet, Inc.
FDOT record

The route, raised from the 2D map

≈ 6.8 miN1 mi
Approximate route from FDOT construction data · SR 5.

Scope of Work

  • Bridge & Structures

SR5/US1 OVERSEAS HWY SEVEN MILE BRIDGE OVER MOSER CHANNEL- B R# 900101 - BRIDGE-REPAIR/REHABILITATION

Categories derived from the FDOT Work Program work-mix code for this project.

Contracts & Awards

Prime contractor
Freyssinet, Inc.FDOT
Contract
E6P31FDOT
Construction contract value
$17.7MDerived
FDOT project manager
Tony SabbagFDOT

CEI, subconsultants, project team contacts and award history are part of Pro.

Project Network Preview

2

Organizations

1

Key Contacts

24

Related Projects

Recent Activity

  1. Status changed · In procurement → Under ConstructionAug 20, 2026

Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.

Opportunity Signals

22
contracts up for bid
$74.3M
value at stake
2030-02
next expiry

Counts and totals only. Incumbents, contract rows and bid timing are Pro.

Don’t get scooped on this work.

$74.3M of work bids here by 2030 — be first to know the moment each RFQ drops.

  • Email notifications
  • Activity dashboard
  • Cancel anytime

Opportunity announcements

New RFQs, RFPs, Solicitations

Contract awards

Winners, Award values, Award dates

Team & consultant changes

New firms, Teaming updates, Incumbent changes

Milestone & funding updates

Funding changes, Key milestones

Related corridor activity

New corridor projects

Unlock with TransitAtlas Pro to get full project intelligence and alerts.

Programmed in the FDOT Five-Year Work Program (FY 2026), managed by FDOT District Six. Detailed fact sheets and outreach materials are published once construction approaches.