Under Construction FDOT D5 Orange County, FL I-4Roadway Improvements
Last updated Oct 15, 2026
Project summary
Interchange on I-4 in Orange County.
Lane Construction Corporation (The) has been building it for FDOT District Five since Oct 6, 2023. FDOT estimates the contract finishes on Aug 12, 2028.
Construction cost (this project)
$98.1M
Sum of 4 FDOT line items
Contract E55B8
$117.8M
Covers 4 projects
Prime contractor
Lane Construction Corporation (The)
FDOT record
Oct 6, 202364% of contract time elapsed · 629 days from todayAug 12, 2028
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$88.1M of work bids here by 2028 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2023), managed by FDOT District Five. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressOct 6, 2023 – Aug 12, 2028
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 0.8 miN0.1 mi
RoadwayI-4
CountyOrange County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
I-4/SR-400 From East Of SR-535 To West Of SR-535
Interchange · Planning & Study
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed64%
Of the 58 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion629 days
Remaining against FDOT's estimated contract completion date.
Data freshness37 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 4 projects)Σ FDOT Active Construction lines · contract E55B8
$117.8M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$98.1M
Phase line item (44891415201)FDOT Active Construction
$89.2M
Contract line items
448914-1-52-01This phase$89.2M
448914-1-52-02$8.9M
448914-1-52-03$22.3K
448914-1-52-04$48.9K
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗