I-275/SR 93 Sb/I-4/Sr 400 WB From N Of Morgan St To W Of N 12Th St
Under Construction FDOT D7 Hillsborough County, FL I-275Interchange
Last updated Oct 15, 2026
Project summary
Interchange on I-275 in Hillsborough County.
Lane Construction Corporation (The) has been building it for FDOT District Seven since Sep 26, 2022. FDOT estimates the contract finishes on Feb 21, 2027.
Construction cost (this project)
$113.9M
Sum of 1 FDOT line item
Contract E7R70
$227.6M
Covers 3 projects
Prime contractor
Lane Construction Corporation (The)
FDOT record
Sep 26, 202294% of contract time elapsed · 90 days from todayFeb 21, 2027
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$111.8M of work bids here by 2026 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2025), managed by FDOT District Seven. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressSep 26, 2022 – Feb 21, 2027
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 0.5 miN0.1 mi
RoadwayI-275
CountyHillsborough County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
I-275/SR 93 Sb/I-4/Sr 400 WB From N Of Morgan St To W Of N 12Th St
Interchange · Capacity / Add Lanes
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed94%
Of the 53 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion90 days
Remaining against FDOT's estimated contract completion date.
Data freshness39 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 3 projects)Σ FDOT Active Construction lines · contract E7R70
$227.6M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$113.9M
Phase line item (44505625201)FDOT Active Construction
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗