I-4 (SR 400) At SR 33 Interchange Modification
Project Summary
I-4 (SR 400) At SR 33 Interchange Modification
Scope of Work
- Interchange
- Capacity / Add Lanes
I-4 (SR 400) AT SR 33 INTERCHANGE MODIFICATION - INTERCHANGE - ADD LANES
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
- Prime contractor
- Lane Construction Corporation (The)FDOT
- Contract
- T1899FDOT
- Construction cost (this project)
- $118.4MDerived
- FDOT project manager
- David JonesFDOT
CEI, subconsultants, project team contacts and award history are part of Pro.
Project Location
Approximate route from FDOT construction data · I-4.
Project Network Preview
Organizations
Key Contacts
Related Projects
Related Projects
Same Work Program item
Same contract
Opportunity Signals
- 14
- contracts up for bid
- $46.4M
- value at stake
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$46.4M of work bids here — be first to know the moment each RFQ drops.
Email notifications Activity dashboard Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Programmed in the FDOT Five-Year Work Program (FY 2024), managed by FDOT District One. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete DesignComplete ProcurementComplete- ConstructionIn ProgressJan 6, 2025 – May 17, 2029
- CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
- RoadwayI-4
- CountyPolk County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
I-4 (SR 400) At SR 33 Interchange Modification
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Aug 25, 2026- Contract time elapsed39%
Of the 52 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
- Estimated completion979 days
Remaining against FDOT's estimated contract completion date.
- Data freshness17 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
- Contract total (covers 6 projects)Σ FDOT Active Construction lines · contract T1899
- $192.5M
- Construction cost (this project)Σ FDOT Active Construction lines for this project
- $118.4M
- Phase line item (43018535201)FDOT Active Construction
- $118.4M
Contract
FDOT record- Contract
- T1899
- Prime contractor
- Lane Construction Corporation (The)
- FDOT project manager
- David Jones
- Contract status
- Active
- Contract time (bid)
- 1,500 days
- Time added by adjustments
- 103 days
- Federal project number
- D124056B
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
- Project milestone: Estimated completionUpcomingMay 27, 2029FDOT Construction Contracts
- Data sync: FDOT Active Construction re-readAug 25, 2026Scheduled data sync — no project fact necessarily changed
- Data sync: FDOT Work Program re-readAug 25, 2026Scheduled data sync — no project fact necessarily changed
- Data sync: FDOT Construction Contracts re-readAug 18, 2026Scheduled data sync — no project fact necessarily changed
- Project milestone: Work beganJan 6, 2025FDOT Construction Contracts
- Project milestone: Notice to proceedOct 17, 2024FDOT Construction Contracts
- Project milestone: ExecutedSep 19, 2024FDOT Construction Contracts
- Project milestone: LetAug 14, 2024FDOT Construction Contracts
- Project milestone: Projected lettingAug 14, 2024FDOT Construction Contracts
Related Projects
Same Work Program item
Same contract
Dates & milestones
- Construction start
- Jan 6, 2025
- Contract completion (estimated)
- May 17, 2029
- Program year
- FY 2024
Identifiers
- FPID
- 430185-3-52-01
- Contract number
- T1899
- Work Program item
- 430185
- District
- FDOT D1
- County
- Polk
- Road
- I-4
- Work mix (FDOT)
- Interchange - Add La
- FDOT status name
- UNDER CONSTRUCTION
Sources & Data Confidence
View source details (21 facts)Hide source details
Not available for this project: district project page, federal funding.
| Fact | Value | Source | As of |
|---|---|---|---|
| Project name | I-4 (SR 400) At SR 33 Interchange Modification | FDOT Work Program | Aug 25, 2026 |
| Status | Under Construction | Derived from FDOT Work Program status (UNDER CONSTRUCTION) | Aug 25, 2026 |
| FDOT status | UNDER CONSTRUCTION | FDOT Work Program | Aug 25, 2026 |
| FPID | 430185-3-52-01 | FDOT Work Program | Aug 25, 2026 |
| Work Program item | 430185 | FDOT Work Program | Aug 25, 2026 |
| County | Polk | FDOT Work Program | Aug 25, 2026 |
| Road | I-4 | FDOT Work Program | Aug 25, 2026 |
| Limits | I-4 (SR 400) At SR 33 Interchange Modification | FDOT Work Program | Aug 25, 2026 |
| Scope of work | Interchange · Capacity / Add Lanes | Derived from FDOT Work Program work mix (Interchange - Add La) | Aug 25, 2026 |
| Program year | FY 2024 | FDOT Work Program | Aug 25, 2026 |
| Contract total (covers 6 projects) | $192.5M | Σ FDOT Active Construction lines · contract T1899 | Aug 25, 2026 |
| Construction cost (this project) | $118.4M | Σ FDOT Active Construction lines for this project | Aug 25, 2026 |
| Phase line item (43018535201) | $118.4M | FDOT Active Construction | Aug 25, 2026 |
| Construction start | 2025-01-06 | FDOT Active Construction | Aug 25, 2026 |
| Contract completion (estimated) | 2029-05-17 | FDOT Active Construction | Aug 25, 2026 |
| Contract number | T1899 | FDOT Construction Contracts | Aug 18, 2026 |
| Contract let | 2024-08-14 | FDOT Construction Contracts | Aug 18, 2026 |
| Notice to proceed | 2024-10-17 | FDOT Construction Contracts | Aug 18, 2026 |
| Prime contractor | Lane Construction Corporation (The) | FDOT Active Construction | Aug 25, 2026 |
| FDOT project manager | David Jones | FDOT Active Construction | Aug 25, 2026 |
| Route geometry | Mapped route | FDOT Active Construction | Aug 25, 2026 |
Every fact in this record links to its published source. Where two sources disagree, both are shown rather than averaged or picked.
Lane closures & detours
Loading closure information…
Source: FDOT Work Zone Data Exchange. Publication is voluntary and may be incomplete.
Project Network
The agency, firms, people and corridors on this project. Hover a row to highlight it, click to recenter, or filter by type in the legend.
14
Upcoming Bids
Confirmed · nearing bid
14
Upcoming Opportunities
CAP-backed · in FDOT D1
$46.4M
Total Opportunity Value
Potential value
—
Next Bid
Soonest incumbent expiry
—
Forecast Horizon
Activity window
Opportunity Signals
Upcoming BidsConfirmed · incumbent contracts nearing bid14 Upcoming OpportunitiesCAP-backed · within FDOT D114
Bid counts are sourced. Upcoming Opportunities are CAP-backed and district-level.
Never miss what happens next.
Monitor this project and we’ll alert you the moment there’s movement—opportunities, awards, funding changes, team updates, and key milestones.
14
Future opportunities
identified
$46.4M
Potential value
Planning
CompleteAward
CompleteConstruction
In ProgressOperations
FutureOpportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Monitor This Project
Your intelligence team, on call.
Real-time alerts
Instant notifications when important updates happen
Activity dashboard
See all project activity in one central place
Weekly intelligence digest
Curated summary of what matters most
Unlimited project tracking
Follow all the projects you care about