State Road (S.R.) 9/I-95 Ramps Safety Improvement Project at S.R. 704/Okeechobee Boulevard, S.R. 786/PGA Boulevard, and S.R. 706/Indiantown Road
Under ConstructionConstruction complete FDOT D4 Palm Beach County, FL SR 9 I-95Resurfacing
Last updated Oct 15, 2026
Project summary
Resurfacing on S.R. 9/I-95 in Palm Beach County (0.902 miles).
S.R. 704/Okeechobee Boulevard eastbound to I-95 northbound; I-95 northbound to S.R. 786/PGA Boulevard westbound; I-95 northbound to S.R. 706/Indiantown Road westbound; I-95 southbound to S.R. 706/Indiantown Road eastbound
Ranger Construction Industries, Inc. has been building it for FDOT District Four since Jan 12, 2026. FDOT's estimated contract completion was May 2, 2026.
Construction contract value
$1.2M
Contract T4720, this project only
Prime contractor
Ranger Construction Industries, Inc.
FDOT record
Jan 12, 2026100% of contract time elapsed · 206 days past the estimateMay 2, 2026
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$125.7M of work bids here by 2029 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Fact sheets, public-meeting materials, and construction updates are published by FDOT District Four. View on the source site
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressJan 12, 2026 – May 2, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 0.3 miN5 mi
RoadwaySR 9
CountyPalm Beach County
Length0.902 miles
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
S.R. 704/Okeechobee Boulevard eastbound to I-95 northbound; I-95 northbound to S.R. 786/PGA Boulevard westbound; I-95 northbound to S.R. 706/Indiantown Road westbound; I-95 southbound to S.R. 706/Indiantown Road eastbound
0.902 miles
Project length
Resurfacing · Safety
Scope of work
Construction complete
FDOT status
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed100%
Of the 4 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion206 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Cost sourcesDiffer by 1.5%
Measured between the district’s published project cost and the FDOT feed figure. Below the threshold used to flag a conflict — shown so the gap is visible rather than inferred from the absence of a warning.
Data freshness39 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract T4720
$1.2M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$1.2M
Project costFDOT district project site
$1.2M
Phase line item (44928015201)FDOT Active Construction
$1.2M
$1.4M / mileConstruction contract value ÷ 0.902 miles
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
Data sync: FDOT Active Construction re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Work Program re-readSep 16, 2026
Scheduled data sync — no project fact necessarily changed
Detected change: Status changedAug 20, 2026
Under Construction → Complete
Data sync: FDOT Construction Contracts re-readAug 18, 2026
Scheduled data sync — no project fact necessarily changed