SR 5/Us-1/South Dixie Highway At SW 37 Ave
Project summary
Traffic Operations on SR 5 in Miami-Dade County.
Agc Electric, Inc. is building it for FDOT District Six. FDOT's estimated contract completion was Jun 1, 2026.
- Construction contract value
- $999K
- Contract E6P76, this project only
- Prime contractor
- Agc Electric, Inc.
- FDOT record
The route, raised from the 2D map
© OpenStreetMap contributors
Scope of Work
Traffic Operations
SR 5/US-1/SOUTH DIXIE HIGHWAY AT SW 37 AVE - TRAFFIC OPS IMP ROVEMENT
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
- Prime contractor
- Agc Electric, Inc.FDOT
- Contract
- E6P76FDOT
- Construction contract value
- $999KDerived
- FDOT project manager
- Carmen NegronFDOT
Project Network Preview
Organizations
Key Contacts
Related Projects
Recent Activity
- Status changed · In procurement → Under ConstructionAug 20, 2026
Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.
Related Projects
Nearby
- SR 90/SW 7Th Street At SW 14Th AvenueMiami-Dade County · 2021 – 20263.3 mi away
- SR 976/Bird Road/Sw40 St From W Of Laguna St To West Of SW 38 AveMiami-Dade County · 20260.3 mi away$1.2M
- SR 986/Sunset Driveand SR 826 SB Off RampMiami-Dade County · 20264.4 mi away$993.4K
- SR953/LEJEUNE/SW 42Ave Frm N. Of SR5/S. Dixie Hwy To N. Of Altara AveMiami-Dade County · 20260.5 mi away$2.5M
Opportunity Signals
- 22
- contracts up for bid
- $74.3M
- value at stake
- 2030-02
- next expiry
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$74.3M of work bids here by 2030 — be first to know the moment each RFQ drops.
Email notifications Activity dashboard Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Programmed in the FDOT Five-Year Work Program (FY 2026), managed by FDOT District Six. Detailed fact sheets and outreach materials are published once construction approaches.
Project Timeline
PlanningComplete DesignComplete ProcurementComplete- ConstructionIn ProgressJun 1, 2026
- CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
- RoadwaySR 5
- CountyMiami-Dade County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
SR 5/Us-1/South Dixie Highway At SW 37 Ave
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026- Estimated completion175 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
- Data freshness38 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
- Construction contract valueΣ FDOT Active Construction lines · contract E6P76
- $999K
- Construction cost (this project)Σ FDOT Active Construction lines for this project
- $999K
- Phase line item (44772315201)FDOT Active Construction
- $999K
Contract
FDOT record- Contract
- E6P76
- Prime contractor
- Agc Electric, Inc.
- FDOT project manager
- Carmen Negron
- Contract status
- Active
- Contract time (bid)
- 180 days
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
- Project milestone: Estimated completionUpcomingJan 8, 2027FDOT Construction Contracts
- Data sync: FDOT Active Construction re-readOct 15, 2026Scheduled data sync — no project fact necessarily changed
- Data sync: FDOT Work Program re-readSep 16, 2026Scheduled data sync — no project fact necessarily changed
- Detected change: Status changedAug 20, 2026In procurement → Under Construction
- Data sync: FDOT Construction Contracts re-readAug 18, 2026Scheduled data sync — no project fact necessarily changed
- Project milestone: Work beganJul 13, 2026FDOT Construction Contracts
- Project milestone: Notice to proceedDec 4, 2025FDOT Construction Contracts
- Project milestone: ExecutedNov 3, 2025FDOT Construction Contracts
- Project milestone: LetSep 25, 2025FDOT Construction Contracts
- Project milestone: Projected lettingSep 25, 2025FDOT Construction Contracts
What Changed
- Aug 20, 2026Status changedIn procurement → Under Construction
Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.
Related Projects
Nearby
- SR 90/SW 7Th Street At SW 14Th AvenueMiami-Dade County · 2021 – 20263.3 mi away
- SR 976/Bird Road/Sw40 St From W Of Laguna St To West Of SW 38 AveMiami-Dade County · 20260.3 mi away$1.2M
- SR 986/Sunset Driveand SR 826 SB Off RampMiami-Dade County · 20264.4 mi away$993.4K
- SR953/LEJEUNE/SW 42Ave Frm N. Of SR5/S. Dixie Hwy To N. Of Altara AveMiami-Dade County · 20260.5 mi away$2.5M
Dates & milestones
- Contract completion (estimated)
- Jun 1, 2026
- Program year
- FY 2026
Identifiers
- FPID
- 447723-1-52-01
- Contract number
- E6P76
- Work Program item
- 447723
- District
- FDOT D6
- County
- Miami-Dade
- Road
- SR 5
- Work mix (FDOT)
- Traffic Ops Improvem
- FDOT status name
- UNDER CONSTRUCTION
Sources & Data Confidence
View source details (20 facts)Hide source details
Not available for this project: district project page, federal funding.
| Fact | Value | Source | As of |
|---|---|---|---|
| Project name | SR 5/Us-1/South Dixie Highway At SW 37 Ave | FDOT Work Program | Sep 16, 2026 |
| Status | Under Construction | Derived from FDOT Work Program status (UNDER CONSTRUCTION) | Sep 16, 2026 |
| FDOT status | UNDER CONSTRUCTION | FDOT Work Program | Sep 16, 2026 |
| FPID | 447723-1-52-01 | FDOT Work Program | Sep 16, 2026 |
| Work Program item | 447723 | FDOT Work Program | Sep 16, 2026 |
| County | Miami-Dade | FDOT Work Program | Sep 16, 2026 |
| Road | SR 5 | FDOT Work Program | Sep 16, 2026 |
| Limits | SR 5/Us-1/South Dixie Highway At SW 37 Ave | FDOT Work Program | Sep 16, 2026 |
| Scope of work | Traffic Operations | Derived from FDOT Work Program work mix (Traffic Ops Improvem) | Sep 16, 2026 |
| Program year | FY 2026 | FDOT Work Program | Sep 16, 2026 |
| Construction contract value | $998,959 | Σ FDOT Active Construction lines · contract E6P76 | Oct 15, 2026 |
| Construction cost (this project) | $998,959 | Σ FDOT Active Construction lines for this project | Oct 15, 2026 |
| Phase line item (44772315201) | $998,959 | FDOT Active Construction | Oct 15, 2026 |
| Contract completion (estimated) | 2026-06-01 | FDOT Active Construction | Oct 15, 2026 |
| Contract number | E6P76 | FDOT Construction Contracts | Aug 18, 2026 |
| Contract let | 2025-09-25 | FDOT Construction Contracts | Aug 18, 2026 |
| Notice to proceed | 2025-12-04 | FDOT Construction Contracts | Aug 18, 2026 |
| Prime contractor | Agc Electric, Inc. | FDOT Active Construction | Oct 15, 2026 |
| FDOT project manager | Carmen Negron | FDOT Active Construction | Oct 15, 2026 |
| Route geometry | Mapped route | FDOT Active Construction | Oct 15, 2026 |
Every fact in this record links to its published source. Where two sources disagree, both are shown rather than averaged or picked.
Lane closures & detours
Loading closure information…
Source: FDOT Work Zone Data Exchange. Publication is voluntary and may be incomplete.
Height marks the route; it carries no value
© OpenStreetMap contributors
Project Network
The agency, firms, people and corridors on this project. Hover a row to highlight it, click to recenter, or filter by type in the legend.
22
+2 in last 90 days
Upcoming Bids
Confirmed · nearing bid
21
+2 in last 90 days
Upcoming Opportunities
CAP-backed · in FDOT D6
$74.3M
Total Opportunity Value
Potential by 2030
Feb 2030
Next Bid
Soonest incumbent expiry
2030
Forecast Horizon
Through 2030
Opportunity Signals
Upcoming BidsConfirmed · incumbent contracts nearing bid22 Upcoming OpportunitiesCAP-backed · within FDOT D621
Bid counts are sourced. Upcoming Opportunities are CAP-backed and district-level.
Never miss what happens next.
Monitor this project and we’ll alert you the moment there’s movement—opportunities, awards, funding changes, team updates, and key milestones.
22
Future opportunities
identified
$74.3M
Potential value
by 2030
Planning
CompleteAward
CompleteConstruction
In ProgressOperations
FutureOpportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Monitor This Project
Your intelligence team, on call.
On your dashboard
The project in your watch list, with its latest dated signal
Change alerts
Status, letting and contractor changes in your alerts inbox
Weekly email
A summary in the weeks the project changes