SR 5/Us-1/South Dixie Highway At SW 37 Ave

Under Construction FDOT D6 Miami-Dade County, FL SR 5Roadway Improvements
Last updated Oct 15, 2026

Project summary

Traffic Operations on SR 5 in Miami-Dade County.

Agc Electric, Inc. is building it for FDOT District Six. FDOT's estimated contract completion was Jun 1, 2026.

Construction contract value
$999K
Contract E6P76, this project only
Prime contractor
Agc Electric, Inc.
FDOT record

The route, raised from the 2D map

≈ 0.2 miN0.1 mi
Approximate route from FDOT construction data · SR 5.

Scope of Work

  • Traffic Operations

SR 5/US-1/SOUTH DIXIE HIGHWAY AT SW 37 AVE - TRAFFIC OPS IMP ROVEMENT

Categories derived from the FDOT Work Program work-mix code for this project.

Contracts & Awards

Prime contractor
Agc Electric, Inc.FDOT
Contract
E6P76FDOT
Construction contract value
$999KDerived
FDOT project manager
Carmen NegronFDOT

CEI, subconsultants, project team contacts and award history are part of Pro.

Project Network Preview

2

Organizations

1

Key Contacts

24

Related Projects

Recent Activity

  1. Status changed · In procurement → Under ConstructionAug 20, 2026

Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.

Opportunity Signals

22
contracts up for bid
$74.3M
value at stake
2030-02
next expiry

Counts and totals only. Incumbents, contract rows and bid timing are Pro.

Don’t get scooped on this work.

$74.3M of work bids here by 2030 — be first to know the moment each RFQ drops.

  • Email notifications
  • Activity dashboard
  • Cancel anytime

Opportunity announcements

New RFQs, RFPs, Solicitations

Contract awards

Winners, Award values, Award dates

Team & consultant changes

New firms, Teaming updates, Incumbent changes

Milestone & funding updates

Funding changes, Key milestones

Related corridor activity

New corridor projects

Unlock with TransitAtlas Pro to get full project intelligence and alerts.

Programmed in the FDOT Five-Year Work Program (FY 2026), managed by FDOT District Six. Detailed fact sheets and outreach materials are published once construction approaches.