SR 986/Sunset Driveand SR 826 SB Off Ramp
Project summary
Intersection on SR 986 in Miami-Dade County.
Florida Engineering & Development Corp is building it for FDOT District Six. FDOT's estimated contract completion was May 10, 2026.
- Construction cost (this project)
- $993.4K
- Sum of 1 FDOT line item
- Contract T6609
- $1.7M
- Covers 3 projects
- Prime contractor
- Florida Engineering & Development Corp
- FDOT record
The route, raised from the 2D map
© OpenStreetMap contributors
Scope of Work
Intersection
SR 986/SUNSET DRIVE AND SR 826 SB OFF RAMP - INTERSECTION IM PROVEMENT
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
- Prime contractor
- Florida Engineering & Development CorpFDOT
- Contract
- T6609FDOT
- Construction cost (this project)
- $993.4KDerived
- FDOT project manager
- Milad MansouriFDOT
Project Network Preview
Organizations
Key Contacts
Related Projects
Recent Activity
- Status changed · In procurement → Under ConstructionAug 20, 2026
Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.
Related Projects
Nearby
- Ped Bridge Over SR 90/US 41/SW 8 St And C-4 Canal W Of SW 109 AveMiami-Dade County · 2024 – 20275.3 mi away$38.1M
- SR 5/Us-1/South Dixie Highway At SW 37 AveMiami-Dade County · 20264.4 mi away$999K
- SR 976/Bird Road/Sw40 St From W Of Laguna St To West Of SW 38 AveMiami-Dade County · 20264.3 mi away$1.2M
- SR953/LEJEUNE/SW 42Ave Frm N. Of SR5/S. Dixie Hwy To N. Of Altara AveMiami-Dade County · 20264.0 mi away$2.5M
Opportunity Signals
- 22
- contracts up for bid
- $74.3M
- value at stake
- 2030-02
- next expiry
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$74.3M of work bids here by 2030 — be first to know the moment each RFQ drops.
Email notifications Activity dashboard Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Programmed in the FDOT Five-Year Work Program (FY 2026), managed by FDOT District Six. Detailed fact sheets and outreach materials are published once construction approaches.
Project Timeline
PlanningComplete DesignComplete ProcurementComplete- ConstructionIn ProgressMay 10, 2026
- CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
- RoadwaySR 986
- CountyMiami-Dade County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
SR 986/Sunset Driveand SR 826 SB Off Ramp
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026- Estimated completion198 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
- Data freshness39 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
- Contract total (covers 3 projects)Σ FDOT Active Construction lines · contract T6609
- $1.7M
- Construction cost (this project)Σ FDOT Active Construction lines for this project
- $993.4K
- Phase line item (44936915201)FDOT Active Construction
- $993.4K
Contract
FDOT record- Contract
- T6609
- Prime contractor
- Florida Engineering & Development Corp
- FDOT project manager
- Milad Mansouri
- Contract status
- Active
- Contract time (bid)
- 180 days
- Time added by adjustments
- 10 days
- Federal project number
- D625016B
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
- Project milestone: Estimated completionNov 16, 2026FDOT Construction Contracts
- Data sync: FDOT Active Construction re-readOct 15, 2026Scheduled data sync — no project fact necessarily changed
- Data sync: FDOT Work Program re-readSep 16, 2026Scheduled data sync — no project fact necessarily changed
- Detected change: Status changedAug 20, 2026In procurement → Under Construction
- Data sync: FDOT Construction Contracts re-readAug 18, 2026Scheduled data sync — no project fact necessarily changed
- Project milestone: Work beganMay 11, 2026FDOT Construction Contracts
- Project milestone: Notice to proceedNov 12, 2025FDOT Construction Contracts
- Project milestone: ExecutedOct 14, 2025FDOT Construction Contracts
- Project milestone: LetAug 27, 2025FDOT Construction Contracts
- Project milestone: Projected lettingAug 27, 2025FDOT Construction Contracts
What Changed
- Aug 20, 2026Status changedIn procurement → Under Construction
Detected by comparing FDOT's published data between syncs. Dates are when the change was observed, not necessarily when FDOT made it.
Related Projects
Nearby
- Ped Bridge Over SR 90/US 41/SW 8 St And C-4 Canal W Of SW 109 AveMiami-Dade County · 2024 – 20275.3 mi away$38.1M
- SR 5/Us-1/South Dixie Highway At SW 37 AveMiami-Dade County · 20264.4 mi away$999K
- SR 976/Bird Road/Sw40 St From W Of Laguna St To West Of SW 38 AveMiami-Dade County · 20264.3 mi away$1.2M
- SR953/LEJEUNE/SW 42Ave Frm N. Of SR5/S. Dixie Hwy To N. Of Altara AveMiami-Dade County · 20264.0 mi away$2.5M
Dates & milestones
- Contract completion (estimated)
- May 10, 2026
- Program year
- FY 2026
Identifiers
- FPID
- 449369-1-52-01
- Contract number
- T6609
- Work Program item
- 449369
- District
- FDOT D6
- County
- Miami-Dade
- Road
- SR 986
- Work mix (FDOT)
- Intersection Improve
- FDOT status name
- UNDER CONSTRUCTION
Sources & Data Confidence
View source details (20 facts)Hide source details
Not available for this project: district project page, federal funding.
| Fact | Value | Source | As of |
|---|---|---|---|
| Project name | SR 986/Sunset Driveand SR 826 SB Off Ramp | FDOT Work Program | Sep 16, 2026 |
| Status | Under Construction | Derived from FDOT Work Program status (UNDER CONSTRUCTION) | Sep 16, 2026 |
| FDOT status | UNDER CONSTRUCTION | FDOT Work Program | Sep 16, 2026 |
| FPID | 449369-1-52-01 | FDOT Work Program | Sep 16, 2026 |
| Work Program item | 449369 | FDOT Work Program | Sep 16, 2026 |
| County | Miami-Dade | FDOT Work Program | Sep 16, 2026 |
| Road | SR 986 | FDOT Work Program | Sep 16, 2026 |
| Limits | SR 986/Sunset Driveand SR 826 SB Off Ramp | FDOT Work Program | Sep 16, 2026 |
| Scope of work | Intersection | Derived from FDOT Work Program work mix (Intersection Improve) | Sep 16, 2026 |
| Program year | FY 2026 | FDOT Work Program | Sep 16, 2026 |
| Contract total (covers 3 projects) | $1.7M | Σ FDOT Active Construction lines · contract T6609 | Oct 15, 2026 |
| Construction cost (this project) | $993,361 | Σ FDOT Active Construction lines for this project | Oct 15, 2026 |
| Phase line item (44936915201) | $993,361 | FDOT Active Construction | Oct 15, 2026 |
| Contract completion (estimated) | 2026-05-10 | FDOT Active Construction | Oct 15, 2026 |
| Contract number | T6609 | FDOT Construction Contracts | Aug 18, 2026 |
| Contract let | 2025-08-27 | FDOT Construction Contracts | Aug 18, 2026 |
| Notice to proceed | 2025-11-12 | FDOT Construction Contracts | Aug 18, 2026 |
| Prime contractor | Florida Engineering & Development Corp | FDOT Active Construction | Oct 15, 2026 |
| FDOT project manager | Milad Mansouri | FDOT Active Construction | Oct 15, 2026 |
| Route geometry | Mapped route | FDOT Active Construction | Oct 15, 2026 |
Every fact in this record links to its published source. Where two sources disagree, both are shown rather than averaged or picked.
Lane closures & detours
Loading closure information…
Source: FDOT Work Zone Data Exchange. Publication is voluntary and may be incomplete.
Height marks the route; it carries no value
© OpenStreetMap contributors
Project Network
The agency, firms, people and corridors on this project. Hover a row to highlight it, click to recenter, or filter by type in the legend.
22
+2 in last 90 days
Upcoming Bids
Confirmed · nearing bid
21
+2 in last 90 days
Upcoming Opportunities
CAP-backed · in FDOT D6
$74.3M
Total Opportunity Value
Potential by 2030
Feb 2030
Next Bid
Soonest incumbent expiry
2030
Forecast Horizon
Through 2030
Opportunity Signals
Upcoming BidsConfirmed · incumbent contracts nearing bid22 Upcoming OpportunitiesCAP-backed · within FDOT D621
Bid counts are sourced. Upcoming Opportunities are CAP-backed and district-level.
Never miss what happens next.
Monitor this project and we’ll alert you the moment there’s movement—opportunities, awards, funding changes, team updates, and key milestones.
22
Future opportunities
identified
$74.3M
Potential value
by 2030
Planning
CompleteAward
CompleteConstruction
In ProgressOperations
FutureOpportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Monitor This Project
Your intelligence team, on call.
On your dashboard
The project in your watch list, with its latest dated signal
Change alerts
Status, letting and contractor changes in your alerts inbox
Weekly email
A summary in the weeks the project changes