Programmed in the FDOT Five-Year Work Program (FY 2023), managed by FDOT District Six. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressJan 29, 2019 – May 23, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 1.4 miN0.25 mi
RoadwaySR 836
CountyMiami-Dade County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
SR 836/I-395 From West Of I-95 To Macarthur Cswy Bridge
Bridge & Structures · Capacity / Add Lanes
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Aug 25, 2026
Contract time elapsed100%
Of the 88 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion112 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Data freshness18 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 5 projects)Σ FDOT Active Construction lines · contract E6J53
$677.9M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$610M
Phase line item (25168815201)FDOT Active Construction
$552.6M
Contract line items
251688-1-52-01This phase$552.6M
251688-1-52-02$42.4M
251688-1-52-06$12M
251688-1-52-07$42.7K
251688-1-52-30$2.6M
251688-1-52-31$15K
251688-1-52-32$229.8K
251688-1-52-33$18K
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗