I-95(SR9) Over Nassau River Bridges No720218& No720336
Under Construction FDOT D2 Duval County, FL I-95Roadway Improvements
Last updated Oct 15, 2026
Project summary
Bridge & Structures on I-95 in Duval County.
Superior Construction Company Southeast, LLC has been building it for FDOT District Two since Apr 21, 2022. FDOT's estimated contract completion was Mar 29, 2026.
Construction contract value
$22M
Contract E20F7, this project only
Prime contractor
Superior Construction Company Southeast, LLC
FDOT record
Apr 21, 2022100% of contract time elapsed · 240 days past the estimateMar 29, 2026
The route, raised from the 2D map
Arrow keys pan, plus and minus zoom, Q and E turn. On a touch screen, turn and pinch with two fingers.
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$97.2M of work bids here by 2029 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2023), managed by FDOT District Two. Detailed fact sheets and outreach materials are published once construction approaches.
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressApr 21, 2022 – Mar 29, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 0.1 miN0.1 mi
RoadwayI-95
CountyDuval County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
I-95(SR9) Over Nassau River Bridges No720218& No720336
Bridge & Structures
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed100%
Of the 47 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion240 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Data freshness39 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract E20F7
$22M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$22M
Phase line item (43920115201)FDOT Active Construction
$15.1M
Contract line items
439201-1-52-01This phase$15.1M
439201-1-52-02$6.5M
439201-1-52-03$1.7K
439201-1-52-04$75.6K
439201-1-52-05$67.6K
439201-1-52-06$149.2K
439201-1-52-07$126.5K
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
Data sync: FDOT Active Construction re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Work Program re-readSep 16, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Construction Contracts re-readAug 18, 2026
Scheduled data sync — no project fact necessarily changed