Under Construction Turnpike Citrus County, FLCapacity / Add Lanes
Last updated Oct 15, 2026
Project summary
Capacity / Add Lanes on Suncoast Ii-Phase 3A (Sr589)-Cr 486 To CR 495 in Citrus County.
Superior Construction Company Southeast, LLC has been building it for Florida's Turnpike Enterprise since Aug 26, 2025. FDOT estimates the contract finishes on Feb 15, 2030.
Construction contract value
$195.7M
Contract E8V66, this project only
Prime contractor
Superior Construction Company Southeast, LLC
FDOT record
Aug 26, 202528% of contract time elapsed · 1,182 days from todayFeb 15, 2030
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$156.7M of work bids here by 2028 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2025), managed by Florida's Turnpike Enterprise. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressAug 26, 2025 – Feb 15, 2030
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 5.2 miN1 mi
CountyCitrus County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
Suncoast Ii-Phase 3A (Sr589)-Cr 486 To CR 495
Capacity / Add Lanes
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed28%
Of the 54 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion1,182 days
Remaining against FDOT's estimated contract completion date.
Data freshness37 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract E8V66
$195.7M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$195.7M
Phase line item (44276425201)FDOT Active Construction
$195.7M
Project Activity
Data sync: FDOT Active Construction re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed
Data sync: FDOT Work Program re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed