Widen Tpk(Sr91)- Minneola Intchg To Obrien Rd (Mp279.2-285.8)(4To8Lns)
Under Construction Turnpike Lake County, FLCapacity / Add Lanes
Last updated Oct 15, 2026
Project summary
Capacity / Add Lanes on Widen Tpk(Sr91)- Minneola Intchg To Obrien Rd (Mp279.2-285.8)(4To8Lns) in Lake County.
Lane Construction Corporation (The) has been building it for Florida's Turnpike Enterprise since Nov 13, 2022. FDOT estimates the contract finishes on Dec 29, 2028.
Construction cost (this project)
$241.1M
Sum of 1 FDOT line item
Contract E8T35
$241.1M
Covers 2 projects
Prime contractor
Lane Construction Corporation (The)
FDOT record
Nov 13, 202266% of contract time elapsed · 766 days from todayDec 29, 2028
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$156.7M of work bids here by 2028 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2023), managed by Florida's Turnpike Enterprise. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressNov 13, 2022 – Dec 29, 2028
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 6.6 miN1 mi
CountyLake County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
Widen Tpk(Sr91)- Minneola Intchg To Obrien Rd (Mp279.2-285.8)(4To8Lns)
Capacity / Add Lanes · Reconstruction
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed66%
Of the 74 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion766 days
Remaining against FDOT's estimated contract completion date.
Data freshness39 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Contract total (covers 2 projects)Σ FDOT Active Construction lines · contract E8T35
$241.1M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$241.1M
Phase line item (43578615201)FDOT Active Construction
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗