I-4/SR 400 WB Auxiliary Lane From E Of 50Th St T W Of Mlk Jr Blvd
Project Summary
I-4/SR 400 WB Auxiliary Lane From E Of 50Th St T W Of Mlk Jr Blvd
Scope of Work
- Capacity / Add Lanes
I-4/SR 400 WB AUXILIARY LANE FROM E OF 50TH ST T W OF MLK JR BLVD - ADD AUXILIARY LANE(S)
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
- Prime contractor
- C.W. Roberts Contracting, Inc.FDOT
- Contract
- T7517FDOT
- Construction contract value
- $5.8MDerived
- FDOT project manager
- Farhad ZafaranianFDOT
CEI, subconsultants, project team contacts and award history are part of Pro.
Project Location
Approximate route from FDOT construction data · I-4.
Project Network Preview
Organizations
Key Contacts
Related Projects
Related Projects
Nearby
- I275/I75 From Hillsborough County Line To Hillsborough County LineHillsborough County · 20262.3 mi away$1.8M
- I75/I275/I4 Fr Manatee/Pinellas County Line To Hernando County LineHillsborough County · 20263.4 mi away$1.6M
- Palm River Road From W Of US301/SR43 To E Ofus301/Sr43Hillsborough County · 2025 – 20273.4 mi away$3M
- US301/SR43 From N Of Bloomingdale Ave To S Of Mlk BlvdHillsborough County · 2025 – 20273.1 mi away$21.1M
Opportunity Signals
- 11
- contracts up for bid
- $108M
- value at stake
- 2026-05
- next expiry
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$108M of work bids here by 2026 — be first to know the moment each RFQ drops.
Email notifications Activity dashboard Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Programmed in the FDOT Five-Year Work Program (FY 2025), managed by FDOT District Seven. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete DesignComplete ProcurementComplete- ConstructionIn ProgressJun 19, 2025 – Feb 17, 2026
- CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
- RoadwayI-4
- CountyHillsborough County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
I-4/SR 400 WB Auxiliary Lane From E Of 50Th St T W Of Mlk Jr Blvd
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Aug 25, 2026- Contract time elapsed100%
Of the 8 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
- Estimated completion206 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
- Data freshness17 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
- Construction contract valueΣ FDOT Active Construction lines · contract T7517
- $5.8M
- Construction cost (this project)Σ FDOT Active Construction lines for this project
- $5.8M
- Phase line item (44613115201)FDOT Active Construction
- $5.8M
Contract
FDOT record- Contract
- T7517
- Prime contractor
- C.W. Roberts Contracting, Inc.
- FDOT project manager
- Farhad Zafaranian
- Contract status
- Active
- Contract time (bid)
- 220 days
- Time added by adjustments
- 277 days
- Federal project number
- D724028B
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
- Project milestone: Estimated completionUpcomingOct 25, 2026FDOT Construction Contracts
- Data sync: FDOT Active Construction re-readAug 25, 2026Scheduled data sync — no project fact necessarily changed
- Data sync: FDOT Work Program re-readAug 25, 2026Scheduled data sync — no project fact necessarily changed
- Data sync: FDOT Construction Contracts re-readAug 18, 2026Scheduled data sync — no project fact necessarily changed
- Project milestone: Work beganJun 16, 2025FDOT Construction Contracts
- Project milestone: Notice to proceedJan 9, 2025FDOT Construction Contracts
- Project milestone: ExecutedDec 10, 2024FDOT Construction Contracts
- Project milestone: LetOct 30, 2024FDOT Construction Contracts
- Project milestone: Projected lettingOct 30, 2024FDOT Construction Contracts
Related Projects
Nearby
- I275/I75 From Hillsborough County Line To Hillsborough County LineHillsborough County · 20262.3 mi away$1.8M
- I75/I275/I4 Fr Manatee/Pinellas County Line To Hernando County LineHillsborough County · 20263.4 mi away$1.6M
- Palm River Road From W Of US301/SR43 To E Ofus301/Sr43Hillsborough County · 2025 – 20273.4 mi away$3M
- US301/SR43 From N Of Bloomingdale Ave To S Of Mlk BlvdHillsborough County · 2025 – 20273.1 mi away$21.1M
Dates & milestones
- Construction start
- Jun 19, 2025
- Contract completion (estimated)
- Feb 17, 2026
- Program year
- FY 2025
Identifiers
- FPID
- 446131-1-52-01
- Contract number
- T7517
- Work Program item
- 446131
- District
- FDOT D7
- County
- Hillsborough
- Road
- I-4
- Work mix (FDOT)
- Add Auxiliary Lane(S
- FDOT status name
- UNDER CONSTRUCTION
Sources & Data Confidence
View source details (21 facts)Hide source details
Not available for this project: district project page, federal funding.
| Fact | Value | Source | As of |
|---|---|---|---|
| Project name | I-4/SR 400 WB Auxiliary Lane From E Of 50Th St T W Of Mlk Jr Blvd | FDOT Work Program | Aug 25, 2026 |
| Status | Under Construction | Derived from FDOT Work Program status (UNDER CONSTRUCTION) | Aug 25, 2026 |
| FDOT status | UNDER CONSTRUCTION | FDOT Work Program | Aug 25, 2026 |
| FPID | 446131-1-52-01 | FDOT Work Program | Aug 25, 2026 |
| Work Program item | 446131 | FDOT Work Program | Aug 25, 2026 |
| County | Hillsborough | FDOT Work Program | Aug 25, 2026 |
| Road | I-4 | FDOT Work Program | Aug 25, 2026 |
| Limits | I-4/SR 400 WB Auxiliary Lane From E Of 50Th St T W Of Mlk Jr Blvd | FDOT Work Program | Aug 25, 2026 |
| Scope of work | Capacity / Add Lanes | Derived from FDOT Work Program work mix (Add Auxiliary Lane(S) | Aug 25, 2026 |
| Program year | FY 2025 | FDOT Work Program | Aug 25, 2026 |
| Construction contract value | $5.8M | Σ FDOT Active Construction lines · contract T7517 | Aug 25, 2026 |
| Construction cost (this project) | $5.8M | Σ FDOT Active Construction lines for this project | Aug 25, 2026 |
| Phase line item (44613115201) | $5.8M | FDOT Active Construction | Aug 25, 2026 |
| Construction start | 2025-06-19 | FDOT Active Construction | Aug 25, 2026 |
| Contract completion (estimated) | 2026-02-17 | FDOT Active Construction | Aug 25, 2026 |
| Contract number | T7517 | FDOT Construction Contracts | Aug 18, 2026 |
| Contract let | 2024-10-30 | FDOT Construction Contracts | Aug 18, 2026 |
| Notice to proceed | 2025-01-09 | FDOT Construction Contracts | Aug 18, 2026 |
| Prime contractor | C.W. Roberts Contracting, Inc. | FDOT Active Construction | Aug 25, 2026 |
| FDOT project manager | Farhad Zafaranian | FDOT Active Construction | Aug 25, 2026 |
| Route geometry | Mapped route | FDOT Active Construction | Aug 25, 2026 |
Every fact in this record links to its published source. Where two sources disagree, both are shown rather than averaged or picked.
Lane closures & detours
Loading closure information…
Source: FDOT Work Zone Data Exchange. Publication is voluntary and may be incomplete.
Project Network
The agency, firms, people and corridors on this project. Hover a row to highlight it, click to recenter, or filter by type in the legend.
11
Upcoming Bids
Confirmed · nearing bid
10
Upcoming Opportunities
CAP-backed · in FDOT D7
$108M
Total Opportunity Value
Potential by 2026
May 2026
Next Bid
Soonest incumbent expiry
2026
Forecast Horizon
Through 2026
Opportunity Signals
Upcoming BidsConfirmed · incumbent contracts nearing bid11 Upcoming OpportunitiesCAP-backed · within FDOT D710
Bid counts are sourced. Upcoming Opportunities are CAP-backed and district-level.
Never miss what happens next.
Monitor this project and we’ll alert you the moment there’s movement—opportunities, awards, funding changes, team updates, and key milestones.
11
Future opportunities
identified
$108M
Potential value
by 2026
Planning
CompleteAward
CompleteConstruction
In ProgressOperations
FutureOpportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Monitor This Project
Your intelligence team, on call.
Real-time alerts
Instant notifications when important updates happen
Activity dashboard
See all project activity in one central place
Weekly intelligence digest
Curated summary of what matters most
Unlimited project tracking
Follow all the projects you care about