First Coast Expressway Safety Enhancements (Clay & Duval)(Mp31-Mp45.7)
Under Construction Turnpike Turnpike County, FLSafety
Last updated Oct 15, 2026
Project summary
Safety on First Coast Expressway Safety Enhancements (Clay & Duval)(Mp31-Mp45.7) in Turnpike County.
American Lighting And Signalization, LLC. has been building it for Florida's Turnpike Enterprise since Jul 7, 2025. FDOT's estimated contract completion was Oct 2, 2026.
Construction contract value
$8.4M
Contract E8V11, this project only
Prime contractor
American Lighting And Signalization, LLC.
FDOT record
Jul 7, 2025100% of contract time elapsed · 50 days past the estimateOct 2, 2026
The route, raised from the 2D map
Arrow keys pan, plus and minus zoom, Q and E turn. On a touch screen, turn and pinch with two fingers.
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$156.7M of work bids here by 2028 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2025), managed by Florida's Turnpike Enterprise. Detailed fact sheets and outreach materials are published once construction approaches.
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressJul 7, 2025 – Oct 2, 2026
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 8.4 miN5 mi
CountyTurnpike County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
First Coast Expressway Safety Enhancements (Clay & Duval)(Mp31-Mp45.7)
Safety
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed100%
Of the 15 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion50 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Data freshness37 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract E8V11
$8.4M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$8.4M
Phase line item (44971115201)FDOT Active Construction
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
Data sync: FDOT Active Construction re-readOct 15, 2026
Scheduled data sync — no project fact necessarily changed